Augustan, El Camino and Grosse Sewer and Water Replacement

Estimated Construction Schedule: Slated to begin August, 2018 and is anticipated to be completed August, 2019.
Construction Contract Amount: Pending
Project ID #: 1568
Description: This project is part of the replacement of the Grace neighborhood water and sewer mains. This project will replace aged sewer and water mains in Augustan Avenue, El Camino Way from Grosse Avenue to Augustan Avenue, and in Grosse Avenue from El Camino Way to Dowling Court. This project will abandon an inaccessible backyard easement and re-plumb the tributary lots to the public sewer in the street. Ten dpdestrian ramps will be replaced. All streets will be reconstructed.

Design status: August 2017: 40% Design Plans have been completed.

Contacts:

Andrew Wilt
Associate Civil Engineer
City of Santa Rosa
(707)543-4519
awilt@srcity.org

Eric Frye
Quality Control Associate
City of Santa Rosa

EFrye@srcity.org

Dennis Dalby
Principal
Civil Design Consultants
(707) 542-4820
dennis@civildesignconsultants.com
Click for larger image
Project Image

Note: All dates and times are subject to change.