Capital Improvement Project


Santa Rosa Cmplt Sts Road Diet on Transit Corridor

Estimated Construction Schedule: Slated to begin August, 2017 and is anticipated to be completed November, 2017.
Construction Contract Amount: $1,623,810
Project ID #: 1870
Description: This project will repave W. Third Street from 1,100 feet west of Dutton Avenue to Roberts Avenue and Mendocino Avenue from Steele Lane to Administration Drive. Curb ramps will be constructed to meet current standards in both locations. W. Third Street will be restriped to include a single travel lane in each direction, a two-way center turn lane, Class-2 bicycle lanes and street parking.

Construction Update Image

Current Status: W. Third Street progress: Curb ramp installations are primarily complete. Paving operations are expected to start soon with potential delays to traffic in the area. Traffic control for the work will remain within 8:30am and 4:00pm Monday through Friday and the work is expected to take 7-8 days once started. Mendocino Ave progress: Curb ramp installations are ongoing minimal delays are expected in the area at this time.

Contacts:

Lisa Welsh
Associate Civil Engineer
City of Santa Rosa
(707)543-3909
LWelsh@srcity.org

Bernie Alabona
Civil Engineering Tech III
City of Santa Rosa

BAlabona@srcity.org

Team Ghilotti
Phone: (707) 763-8700
Fax: (707) 763-8711

Robert E. Lee
Superintendent
Team Ghilotti
(707)778-8919
(415)720-2044
RobertL@TeamGhilotti.com

Mike Sciacca
Team Ghilotti
(707)799-1994
(415)720-9258

Karen Toso
Project Manager
Team Ghilotti
(707)789-7086
(415)720-6602
KarenT@TeamGhilotti.com

Correspondence:
Advanced Project Notice-3rd Street
Advanced Project Notice-3rd Street (in Spanish)
Advanced Project Notice-Mendocino Ave
Advanced Project Notice-Mendocino Ave (in Spanish)
Imminent Construction Notice-3rd St
Imminent Construction Notice-3rd St (in Spanish)
Imminent Construction Notice-Mendocino Ave
Imminent Construction Notice-Mendocino Ave (in Spanish)

Other Information:
#C01870 Invitation for Bids (IFB)
#C01870 Bid Tab
Click for larger image
Project Image

Note: All dates and times are subject to change.