Alvarado Ave and Vallejo St Water and Sewer Improvements
Estimated Construction Schedule: Slated to begin September, 2018 and is anticipated to be completed August, 2019. Construction Contract Amount: $1,489,199 Project ID #: 2004 |
Description: Phase I will upsize water and sewer mains on Alvarado Avenue and the water main on Vallejo Street between Mt. Olive Drive and Melbrook Way to meet fire flow requirements as identified in the 2014 Water Master Plan. Phase II will improve the sewer junction structure for the Crosstown and Bennett Valley Trunk mains. Two access points will be added to the junction structure to improve visual inspections and facilitate cleaning and maintenance for the entire junction structure and connecting trunk mains. | |
Contacts: Bryan Heinzelman Associate Civil Engineer City of Santa Rosa (707)543-3812 BHeinzelman@srcity.org Correspondence: Advance Construction Notice - Spanish Advance Construction Notice Imminent Construction Notice Imminent Construction Notice - Spanish Other Information: C02004 Invitation for Bids (Information only - see Planet Bids for bidding) C02004 Plans (Information only - see PlanetBids for bidding) C02004 Bid Results |
Click for larger image |