City of Santa Rosa image CIP

Capital Improvement Project


Alvarado Ave and Vallejo St Water and Sewer Improvements

Estimated Construction Schedule: Slated to begin September, 2018 and is anticipated to be completed August, 2019.
Construction Contract Amount: $1,489,199
Project ID #: 2004
Description: Phase I will upsize water and sewer mains on Alvarado Avenue and the water main on Vallejo Street between Mt. Olive Drive and Melbrook Way to meet fire flow requirements as identified in the 2014 Water Master Plan. Phase II will improve the sewer junction structure for the Crosstown and Bennett Valley Trunk mains. Two access points will be added to the junction structure to improve visual inspections and facilitate cleaning and maintenance for the entire junction structure and connecting trunk mains.
Contacts:

Bryan Heinzelman
Associate Civil Engineer
City of Santa Rosa
(707)543-3812
BHeinzelman@srcity.org

Correspondence:
Advance Construction Notice - Spanish
Advance Construction Notice
Imminent Construction Notice
Imminent Construction Notice - Spanish

Other Information:
C02004 Invitation for Bids (Information only - see Planet Bids for bidding)
C02004 Plans (Information only - see PlanetBids for bidding)
C02004 Bid Results
Click for larger image
Project Image

Note: All dates and times are subject to change.