Finley Aquatic Center Spray Ground and Renovation Project

Estimated Construction Schedule: Slated to begin November, 2023 and is anticipated to be completed May, 2024.
Construction Contract Amount: Pending
Project ID #: 2336
Description: A major upgrade to Finley Aquatic Center including the demolition of the existing wading pool and construction of a new, modern spray ground, new and expanded picnic areas, and upgrades to the pool deck to replace areas in disrepair to ensure compliance with the Americans with Disabilities Act (ADA). Finley Aquatic Center will be closed during construction to avoid impacts to popular summer swim programs at the facility. Construction is scheduled to begin in November 2023 with completion in May 2024.

Construction Update Image

April 8, 2024: Weather is breaking, and we have made progress. Both pools have received their necessary repairs. The Contractor is preparing the site grade around the pools for the new concrete deck - formwork, rebar, and slot drain installation will occur prior to the concrete pour. Diving board supports are being blasted and powder coated at an offsite shop. The Swim Center, Mechanical Building, and existing Concessions Building will be pressure washed this month. The site will continue with implementing weather protection mitigating measures. A revised schedule will be available soon.

More Information: For more information regarding this project, please visit the Park's website: https://www.srcity.org/3671/Finley-Aquatic-Center

Contacts:

Dezire Perez Barbante
Associate Civil Engineer
City of Santa Rosa
(707)543-4203
dperez@srcity.org

Scott Wilkinson
Parks Planner
City of Santa Rosa
(707)583-5789
swilkinson@srcity.org

Tim Miller
Superintendent
WATERWORKS INDUSTRIES, INC
(707)888-9366
tim@waterworksindustries.com

Correspondence:
C02336 Invitation for Bid (for information only-see PlanetBids for bidding)
C02336 Plans (for information only-see PlanetBids for bidding)
1991 Record Plans
Bid Tabs C02336