Capital Improvement Project


Roseland Pavement Maintenance- 2024

Estimated Construction Schedule: Slated to begin July, 2024 and is anticipated to be completed October, 2024.
Construction Contract Amount: Pending
Project ID #: 2383
Description: This project will do pavement repair with digout and top with cape seal at various annexed areas in Roseland. All curb ramps within the project limits will be upgraded to the current ADA standards.

Construction Update Image

August 2024: This project has been awarded to Ghilotti Brothers. The slated construction will start in August 2024. A total 33 curb ramps will be upgraded to the current ADA standards. Approximately 2 miles of residental streets will be cape sealed. A cape seal is a two-steps preventive pavement maintenance in which the selected pavement surface is laid with chip seal and topped with slurry seal. Once cured, all new striping will be reinstated to their original configurations. This project will last approximately 8-10 weeks.

Construction Schedule: Please check this website frequently because all construction schedule will be posted here especially when the two-steps cape seal process begins.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Sam Martinez
Civil Engineering Technician
City of Santa Rosa
(707)543-3841
Smartinez@srcity.org

Correspondence:
Advanced Project Notice
Advanced Project Notice Spanish
C02383 Bid Tabs
C02383 Imminent Construction Notice
C02383 Imminent Construction Notice Esp

Other Information:
C02383 Invitation for Bids (for invitation only-see PlanetBids for bidding)
Click for larger image
Project Image

Note: All dates and times are subject to change.