City of Santa Rosa image CIP

Capital Improvement Project


Fulton Rd Reconstruction - Occidental Rd to W 3rd St

Estimated Construction Schedule: Slated to begin June, 2019 and is anticipated to be completed February, 2020.
Construction Contract Amount: $3,824,038
Project ID #: 780
Description: This project will reconstruct Fulton Rd. between Occidental Rd. and W. 3rd St. using portland cement concrete technology, replace deteriorated storm drain pipe near Darla Drive, install a new sewer manhole and update pedestrian ramps to current ADA standards. This project will improve safety and reduce ongoing maintenance costs.

Construction Update Image

Construction Update 2-26-20: Striping operations are complete. Contractor needs to repair shrinkage cracks on the pavement but has not provided a schedule to perform this work.

Contacts:

Gregory Dwyer
Associate Civil Engineer
City of Santa Rosa
(707)543-3838
GDwyer@srcity.org

Tom Gorman
Senior Construction Manager
Kennedy Jenks
707-888-8064
tomgorman@kennedyjenks.com

Correspondence:
Advance Notice Letter
Imminent Construction Notice

Other Information:
Invitation for Bids *NOT FOR BIDDING PURPOSES*
Plans
Bid Tab


Measure M Image


SB1 Image

Click for larger image
Project Image

Note: All dates and times are subject to change.