Fulton Rd Reconstruction - Occidental Rd to W 3rd St

Estimated Construction Schedule: Slated to begin June, 2019 and is anticipated to be completed October, 2019.
Construction Contract Amount: Pending
Project ID #: 780
Description: This project will reconstruct Fulton Rd. between Occidental Rd. and W. 3rd St. using asphalt cement concrete or roller compacted concrete technology, replace deteriorated storm drain pipe near Darla Drive, install a new sewer manhole and update pedestrian ramps to current ADA standards. Roller compacted concrete has the benefit of reduced costs and longer service life. This project will improve safety and reduce ongoing maintenance costs.

Additional News: Bids opened in July 2018. Expect City Council action on contract award in early November 2018.

Contacts:

Gregory Dwyer
Associate Civil Engineer
City of Santa Rosa
(707)543-3838
GDwyer@srcity.org

Correspondence:
Advance Notice Letter

Other Information:
Bid Tab


Measure M Image

Click for larger image
Project Image

Note: All dates and times are subject to change.