Fulton Rd Reconstruction - Occidental Rd to W 3rd St

Estimated Construction Schedule: Slated to begin June, 2019 and is anticipated to be completed October, 2019.
Construction Contract Amount: $3,824,038
Project ID #: 780
Description: This project will reconstruct Fulton Rd. between Occidental Rd. and W. 3rd St. using roller compacted concrete technology, replace deteriorated storm drain pipe near Darla Drive, install a new sewer manhole and update pedestrian ramps to current ADA standards. Roller compacted concrete has the benefit of reduced costs and longer service life. This project will improve safety and reduce ongoing maintenance costs.

Construction Update Image

Construction Update 7-25-19: Contractor has completed the storm drain manhole, sanitary sewer pipe and manhole work. Contractor is finishing up remaining pedestrian ramp construction and electrical line lowering.

Paving Work: Paving work is scheduled to start on 9/3/19 and be completed on 10/18/19. Detours will be in place during paving work to accommodate either northbound or southbound road closures. One direction will be fully open at all times, but 2-way traffic will not be maintained. The side of the roadway in which paving work is taking place will be closed. Expect delays and take alternate routes if possible.

Contacts:

Gregory Dwyer
Associate Civil Engineer
City of Santa Rosa
(707)543-3838
GDwyer@srcity.org

Greg Loraditch
Civil Engineering Tech III
City of Santa Rosa

GLoraditch@srcity.org

Tom Gorman
Senior Construction Manager
Kennedy Jenks
707-888-8064
tomgorman@kennedyjenks.com

Correspondence:
Advance Notice Letter
Imminent Construction Notice

Other Information:
Invitation for Bids *NOT FOR BIDDING PURPOSES*
Plans
Bid Tab


Measure M Image

Click for larger image
Project Image

Note: All dates and times are subject to change.