City of Santa Rosa image CIP

Capital Improvement Project


Los Alamos Trunk Sewer Replacement Segment 1 (Streamside Dr to Elaine Dr)

Estimated Construction Schedule: Slated to begin May, 2023 and is anticipated to be completed February, 2025.
Construction Contract Amount: Pending
Project ID #: 1903
Description: This project will replace approximately 5300 linear feet of the existing Los Alamos Trunk sewer that was installed in the 1950s that is undersized and in poor condition. The new trunk sewer will be 24-inches in diameter and will generally be installed adjacent to the existing alignment between Streamside Dr and Elaine Dr through private property and along Mission Circle and Quigg Dr. An above-ground sewer bypass system will be installed for short durations at certain locations before being relocated as it follows the construction progress along the alignment. To minimize both public and business impacts, a portion of the work along Mission Circle is conditioned night work and the proposed water improvements serving 4920 and 4934 HWY 12 are conditioned weekend work.

Construction Update Image

Fall 2024: Onsite Construction Inspector is Adam Dagler 707-328-5743. The underground sewer improvements are essentially installed with minor corrections being made. Surface improvements to the east of Quigg Dr are completed except for fence and gate repairs and small areas of AC repair and the site has been prepared for fall weather. Concrete crosswalk replacments on Quigg Dr are scheduled for end of October and early November. Setting up for paving operation. Night work re-starting Nov 24th for Mission Circle. For up to date construction related information please visit the special project website www.LosAlamosSewerProject.com

Contacts:

Andrew Wilt
Associate Civil Engineer
City of Santa Rosa
(707)543-3878
awilt@srcity.org

Dave Keck
Quality Control Associate
City of Santa Rosa
+1 (707) 481-4312
dkeck@srcity.org

Mike Janet
Consultant Construction Manager
Coastland
707-494-6464
janet@dccm.com

Ben Bryant, PE
Consultant Design Engineer
Brelje and Race
707-576-1322
Bryant@brce.com

TEAM GHILOTTI INC.
Phone: (707) 763-8700
Fax: (707) 763-8711

Matt Verke
Contractor Superintendent
TEAM GHILOTTI INC.
(707)763-8700
mattv@teamghilotti.com

Joe Moreira
Contractor Project Manager
TEAM GHILOTTI INC.
(707)763-8700

Correspondence:
Initial Study and Mitigated Negative Declaration
Advance Project Notice - English
Advance Project Notice - Spanish
Geotechnical Information Report
C01903 Invitation for Bids (for information only-see PlanetBids for bidding)
Los Alamos Trunk Sewer Initial Study
C01903 Plans (for information only-see PlanetBids for bidding)
Tree Survey Report
Bid Tabs
Imminent Construction Notice - English
Imminent Construction Notice - Spanish

Other Information:
Report - Biological Resources - Phase 1
Biological Resources - Phases 2, 3, and 4
Report - Cultural Resources - Phase 1
Cultural Resources - Phases 2, 3, and 4
Geotechnical Report - Overall
Geotechnical Report- Phase 1
Tree Survey - Phase 1
Click for larger image
Project Image

Note: All dates and times are subject to change.