Franklin Avenue Pedestrian Path
Estimated Construction Schedule: Slated to begin August, 2019 and is anticipated to be completed October, 2019. Construction Contract Amount: $293,666 Project ID #: 779 |
Description:
Construct a sidewalk on the west side of Franklin Avenue between Monroe Avenue and Terrace Way. A pedestrian crossing from Terrace Way across Franklin Avenue will be installed along with ADA ramp upgrades.
|
|
Contacts: Gregory Dwyer Associate Civil Engineer City of Santa Rosa (707)543-3838 GDwyer@srcity.org Jason Balatti Construction Manager Green Valley Consulting Engineers 707-889-6678 jasonb@gvalley.com Richard Owens Contractor Siri Grading & Paving 707-481-5421 siriginc@aol.com Richard Owens SIRI GRADING AND PAVING, INC (707)481-5421 Correspondence: Advance Project Notice Imminent Construction Notice Imminent Construction Notice - Spanish Other Information: Invitation for Bids *Not for Bidding Purposes* Plans *Not for Bidding Purposes* Bid Tab |
Click for larger image![]() |