Sewer Main Lining, Manhole and Lateral Rehab At Various Locations 2016
Estimated Construction Schedule:
Slated to begin July, 2017 and is anticipated to be completed July, 2018.
Construction Contract Amount:
$2,792,000
Project ID #:
1944
Description:
This project will focus on the rehabilitation and/or improvement of sewer mains at various locations in the city. The project will rehabilitate approximately 5,685 feet of pipeline by cured-in-place pipe (CIPP) lining inserted into the existing sewer main pipe at 11 locations throughout the city; 41 manholes are to be rehabilitated and/or improved that are either connected to the pipelines to be CIPP lined or at locations selected by the City; and 6 sewer laterals are to be rehabilitated at three of the project locations.
Contacts:
Cy Penry
Civil Engineering Tech III
City of Santa Rosa
(707)543-4205
CPenry@srcity.org