Capital Improvement Projects List

Image NOTE: The list of public facilities improvement projects shown below contains projects that have completed the necessary budgetary and environmental approval process, as well as those proposed for construction. Appearance of a project on this list does not constitute final approval of any project. Each project is subject to environmental and engineering review to be conducted in accordance with the applicable requirements of the California Environmental Quality Act (CEQA), and City Code provisions. To find out about a few Recreation & Parks projects not listed here, visit www.srcity.org/parks.

Click a Project ID in the table below to see the project web-page report.

Filtered by Projects with Sewer Component

Down arrow imageClick a column header to turn on sorting. Year/Month.
StatusProjIDTitleDescriptionEst StartEst End
Image
Construction
00189Slater Street and Lewrosa Way Sewer and Water Main Replacement ProjectThis project will replace aged water main and sewer main in Lewrosa Way and in Slater Street from Lewis Road to Dexter Street. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing older deteriorated VCP pipe reduces inflow and infiltration and reduces maintenance costs.The pavement will be reconstructed along Slater Street between Lewis Road and Dexter Street and in Lewrosa Way once mains have been replaced. Nine existing curb ramps will also be replaced.2021/092022/05
Image
Proposed
00284Laguna Treatment Plant Disinfection Improvements ProjectUltraviolet light (UV) is the primary disinfection process for the City of Santa Rosa's Laguna Treatment Plant (LTP). The existing system was commissioned in 1998, has reached the end of its useful life, and no longer has the treatment capacity for peak wet weather sewer flows. This project will replace the existing UV system with a new UV system. Additionally, this project will install an effluent diversion pump station and pipeline to convey effluent to the beginning of the plant for retreatment. This provides greater flexibility for operations and regulatory compliance.2021/112024/12
Image
Proposed
00327Terra Linda and Buena Vista Sewer and Water Replacement - Phase 1This project will upgrade existing 6-inch water mains along Terra Linda Dr. to remediate fire flow deficiencies. Aged sewer mains (1961) will be replaced congruently to minimize the potential for future deficiencies. Water and Sewer mains in Terra Linda Ct. will also be replaced. The pavement will be reconstructed along Terra Linda Dr. to Buena Vista and in Terra Linda Ct. once mains have been replaced. Potholing will be taking place in January 2021 to locate existing utilities in the project area. This information is for design purposes at this stage. Please drive carefully and watch for warning signs where they are conducting potholing activities. ** Note: This project is separate from PID00158 North Trunk Sewer Replacement -Mendocino Ave to Terra Linda Dr2022/062022/10
Image
Construction
00661Pacific Ave Reconstruction - Humboldt St to Montecito AveTo reconstruct Pacific Avenue between Humboldt Street and Montecito Avenue. The project will also include: - Curb ramps will be reconstructed at all intersections to meet current accessibility standards. -Replacement of a short section of sewer main on Pacific Avenue and a sewer main supporting 1320 North Street as well as a large section of the water main. -Replacement of water services and hydrants -Drainage inprovements -Rectangular Rapid Flashing Beacon (RRFB) systems at King Street, Beaver Street and Elizabeth Way/Spring Street intersection. -Video Detection System at Humboldt Street, North Street and McDonald Avenue.2020/112021/11
Image
Proposed
01178Fulton Rd from Guerneville Rd to Piner Rd - Widen to Four LanesThe purpose of this project is to ease future traffic congestion. Fulton Road will be reconstructed and widened to 4 lanes with bike lanes and sidewalks between Guerneville Road and Piner Road. The project includes PG&E Rule 20A underground district, a median island and storm drain improvements.2021/042023/01
Image
Proposed
01521Mendocino Ave Easement South of Dawson Road Sewer Main ReplacementReplace deteriorated and deficient sewer mains in two separate locations: in Dawson Road and along an existing sewer easement perpendicular to Mendocino Avenue. This project will improve approximately 1400 lineal feet of existing 6-inch VCP with a trenchless cured-in-place pipe lining' (CIPP) technology for the alignments in Dawson Road and the existing sewer easement perpendicular to Mendocino Avenue. The existing manholes in both locations will also be rehabilitated. Access and sewer easement acquisitions over 12 parcels are needed for routine maintenance. This system improvement will reduce inflow and infiltration into the sewer system while reducing maintenance costs.N/AN/A
Image
Proposed
01903Los Alamos Trunk Replacement: Streamside Dr to Elaine DrThis project includes providing the preliminary design and supporting studies for replacement of the existing Los Alamos sewer trunk from Streamside Drive to Melita Drive (approximately 16,000 linear feet (LF)). Construction documents will be prepared for the downstream segment (approximately 5,500 LF) from Streamside Drive to Elaine Drive. The trunk, installed in the 1950's is undersized and is in poor condition. This project will provide more capacity to help prevent overflows, increase reliability, and reduce maintenance. In addition, it will be re-aligned out of yards and further away from the creek where practical. Relocation of the water main may be necessary in certain locations to create adequate separation from proposed sewer line.2022/042023/08
Image
Proposed
01904Los Alamos Trunk Replacement: Elaine Dr to Melita Rd at Santa Rosa CreekThe purpose of this project is to replace an outdated and undersized section of the Los Alamos Sewer Trunk, which runs north of and parallel to Santa Rosa Creek from Elaine Drive to Melita Road. This project will provide trunk capacity, increase reliability and reduce maintenance. Relocation of the water main to create adequate separation from proposed sewer line is anticipated.2024/042025/08
Image
Proposed
02041Cleveland Ave, A, B, 7th and 8th Street Lateral Installation and Sewer Main AbandonmentThis project will abandon approximately 700 feet of clay sewer main on the west side of Cleveland between Ridgway Avenue and Carrillo Street by transferring 23 laterals to an existing PVC sewer trunk on the east side of Cleveland Avenue. Additionally, this project will include sewer system improvements for 7th Street and B Street. The work on 7th Street will abandon 540 feet of clay sewer main and transfer 2 laterals to an existing sewer trunk between A Street and B Street. The work on B Street includes replacing a 30-foot section of deteriorated pipe near Healdsburg Avenue. This work will reduce inflow and infiltration and reduce maintenance costs.2021/122022/04
Image
Proposed
02117Fulton Rd Sewer Main Improvements West 3rd St to Santa Rosa CreekEliminate the constrictions in the existing sewer pipe across Santa Rosa Creek between manhole 12 and manhole 13. The existing 18-inch ACP sewer was installed in 1969 under the creek and west of the Fulton Road bridge. The 18-inch ACP sewer was lined with a 14-inch polyethylene (PE) liner in 1985. CCTV video indicates that the PE liner is deformed creating constrictions. Open-cut replacement with a new 8-inch diameter pipe was the method recommended by the consultants RMC/Woodward & Curran in their Technical Memorandum dated February 26, 2018. A cofferdam, fish relocation, and construction area creek flow bypass will likely be necessary.2022/052022/12
Image
Construction
02201Skyfarm A and Hansford Court Lift Station ReconstructionTwo lift stations were severely damage during the Tubbs Fire. One is located on SkyFarm Drive near Saint Andrews Drive and the other at the end of Hansford Court. They both must be reconstructed.2020/082021/07
Image
Construction
02208Fire-Related Repairs of Utility StationsSeveral potable water stations, reservoirs and sewer lift stations sustained damage during the Tubbs Fire. This project will undertake rehabilitation efforts at the affected sites.2020/072021/07
Image
Proposed
02284West College Storage Facility Pumping ImprovementsWest College Wet Weather Facility storage basins allow the City to temporarily divert storm flows from the local system in order to balance flows in the Laguna Treatment Plant during winter storm events. Currently, the City rents two trailer mounted diesel powered, vacuum assisted pumps and places them in position at the West College Storage Facility. The City plans to purchase two mobile pumps of similar capacity in lieu of renting and desires to construct permanent facilities to house and operate the pumps including a pad (with built-in containment), roof cover and connection to existing bypass piping.2022/022022/10

Santa Rosa City Hall - 100 Santa Rosa Avenue - Santa Rosa, CA 95404