![]() |
Capital Improvement Projects List
TRANSPORTATION and PUBLIC WORKS | CIP PROGRAM | PROJECTS MAP | BID RESULTS |
Click a Project ID in the table below to see the project web-page report.
Filtered by Projects with Water Component
![]() |
Year/Month. |
Status | ProjID | Title | Description | Est Start | Est End |
---|---|---|---|---|---|
![]() Proposed | 00080 | Emergency Groundwater Supply Development | This is a multi-year project to locate and construct multiple groundwater wells to provide a backup water supply in the event of a natural disaster or other event that disrupts the City's water supply from Sonoma Water. | 2014/01 | 2029/01 |
![]() Construction | 00189 | Slater Street and Lewrosa Way Sewer and Water Main Replacement Project | This project will replace aged water main and sewer main in Lewrosa Way and in Slater Street from Lewis Road to Dexter Street. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing older deteriorated VCP pipe reduces inflow and infiltration and reduces maintenance costs.The pavement will be reconstructed along Slater Street between Lewis Road and Dexter Street and in Lewrosa Way once mains have been replaced. Nine existing curb ramps will also be replaced. | 2021/10 | 2022/03 |
![]() Construction | 00327 | Terra Linda and Buena Vista Sewer and Water Replacement - Phase 1 | This project will upgrade existing 6-inch water mains along Terra Linda Dr. to remediate fire flow deficiencies. Aged sewer mains (1961) will be replaced congruently to minimize the potential for future deficiencies. Water and Sewer mains in Terra Linda Ct. will also be replaced. The pavement will be reconstructed along Terra Linda Dr. to Buena Vista and in Terra Linda Ct. once mains have been replaced. ** Note: This project is separate from PID00158 North Trunk Sewer Replacement -Mendocino Ave to Terra Linda Dr | 2022/05 | 2023/03 |
![]() Proposed | 01178 | Fulton Rd from Guerneville Rd to Piner Rd - Widen to Four Lanes | The purpose of this project is to ease future traffic congestion. Fulton Road will be reconstructed and widened to 4 lanes with bike lanes and sidewalks between Guerneville Road and Piner Road. The Project includes PG&E Rule 20A underground district, roller compact paving, 2 travel lines in each direction, widen sidewalk, bike lanes, median islands and storm drain improvements. | 2022/04 | 2023/12 |
![]() Warranty | 01675 | Montgomery Dr Water System Improvements - Mission Blvd to Jackson Dr | This project will replace a parallel 4" steel water (1947) main and a 6" ACP water main (1969) with a single 8" water main from Montgomery Drive and from Mission Boulevard to Jackson Drive. The 4" steel main is of primary concern and a new single main will reduce maintenance costs. | 2021/03 | 2021/07 |
![]() Proposed | 01903 | Los Alamos Trunk Replacement: Streamside Dr to Elaine Dr | The Los Alamos sewer trunk installed in the 1950's is undersized and is in poor condition. This project will is the first phase of approximately 5,500 LF of a multiphase project that will ultimately replace approximately 16,000 LF. It will provide more capacity to help prevent overflows, increase reliability, and reduce maintenance. In addition, it will be re-aligned out of yards and further away from the creek where practical. Relocation of the water main may be necessary in certain locations to create adequate separation from proposed sewer line. | 2022/09 | 2023/12 |
![]() Proposed | 01999 | Cobblestone Dr Zone R2-R4 Water Main Connection | This project is meant to improve fire protection water flow in the Cobblestone neighborhood only. Several fire hydrants serving approximately 48 homes at the north end of Cobblestone Dr have sub-optimal fire flow. A new 10 inch HDPE pipeline is proposed to connect the existing pipeline in Tillmont Way (Pressure Zone R2) to the existing 6 inch diameter pipeline located in Cobblestone Drive (Pressure Zone R4). In addition, to allow for the ability to isolate the Cobblestone Drive neighborhood water system to create a new pressure zone, approximately 174 LF of 8" diameter PVC water pipe will be installed near the southern end of the Cobblestone Drive loop. | 2022/10 | 2023/02 |
![]() Proposed | 02212 | Seismic Upgrades and Improvements Phase 5 - R9A, R16 and R17 AND VFD and Fire Pump Additions at S16 & S17 | Reservoirs 9A, 16 & 17 have numerous structural deficiencies including ringwall foundation instability, inadequate foundation reinforcing steel, insufficient anchorage embedment, excessive shell stresses in several shell courses and weak interior center support columns. While the operating water levels in each of the reservoirs should be reduced until the deficiencies are addressed, this is not currently being considered as fire protection capabilities for the areas served by the tanks would be compromised. This project may be receiving Hazard Mitigation Grant Funding in Spring of 2018. | 2023/05 | 2025/07 |
![]() Proposed | 02256 | Backup Generators - Water and Wastewater Facilities | This project will replace existing emergency generators and related equipment at 18 water and wastewater facilities in and around Santa Rosa. These upgrades increase generator capacities, update aging equipment, transition facilities to more reliable fuel sources, and decrease greenhouse emissions. This project is part of our larger and ongoing efforts to harden the City's critical infrastructure against potential future hazards, and is funded in part by grants secured from FEMA and the California Office of Emergency Services. | N/A | N/A |