Capital Improvement Project


Building Demolition-Various City Locations

Estimated Construction Schedule: Slated to begin September, 2019 and is anticipated to be completed November, 2019.
Construction Contract Amount: $511,000
Project ID #: 2162
Description: The City owns numerous parcels with existing vacant/dilapidated structures within, and outside of, City limits. Many of these structures exist in locations that are slated for an alternative use and present a liability to the City if they were to remain in place. This project aims to demolish and clear the sites these structures occupy. The demolition of these structures will allow for expanded use of City property, increase the available land area for biosolid land application and add capacity to City owned parking lots. Locations: Doyle Park, Galvin Park, Julliard Park, Roseland Creek Park, 2810 4th Street, 952 Sonoma Ave, 7630 & 7650 Lakeville Hwy., 4090 Walker Rd., 4099 Walker Rd., 1595 Meadow Ln.

Construction Update Image

Anticipated Construction Schedule:
Week of September 16th:
1027 McMinn Avenue

Week of September 23rd:
1370 Burbank Ave
1400 Burbank Avenue

Week of September 30th:
1400 Burbank Avenue
2810 4th Street (Liquor Store)

Week of October 7th:
2810 4th Street (Liquor Store)
1595 Meadow Lane
4099 Walker Avenue

Week of October 14th:
4090 Walker Avenue
Julliard Park (Restroom)

Week of October 21st:
952 Sonoma Avenue
Doyle Park

Week of October 28th:
Doyle Park
7630 Lakeville Highway

Week of November 4th:
7650 Lakeville Highway

Historical Resource Documents: bit.ly/2Wk4BmG

Contacts:

Grant Bailey
Associate Civil Engineer
City of Santa Rosa
(707)543-4508
gbailey@srcity.org

Correspondence:
Advance Construction Notice - 2810 4th St.
Advance Construction Notice - 952 Sonoma Ave
Advance Construction Notice - Doyle Park
Advance Construction Notice - Galvin Park
Advance Construction Notice - Juillliard Park
Advance Construction Notice - 76330 & 7650 Lakeville Hwy
Advance Construction Notice - 4090 & 4099 Walker, 1595 Meadow
Advance Construction Notice - Roseland Creek Park
Advance Construction Notice - Howarth Park
Advance Construction Notice - 2810 4th St. - Spanish
Advance Construction Notice - 952 Sonoma Ave - Spanish
Advance Construction Notice - Doyle Park - Spanish
Advance Construction Notice - Doyle Park - Spanish
Advance Construction Notice - Juillliard Park - Spanish
Advance Construction Notice - 76330 & 7650 Lakeville Hwy - Spanish
Advance Construction Notice - 4090 & 4099 Walker, 1595 Meadow - Spanish
Advance Construction Notice - Roseland Creek Park - Spanish
Advance Construction Notice - Howarth Park - Spanish
Imminent Construction Notice - 2810 4th St
Imminent Construction Notice - 2810 4th St - Spanish
Imminent Construction Notice-952 Sonoma Ave
Imminent Construction Notice-952 Sonoma Ave-Spanish
Imminent Constr. Notice - Doyle Park
Imminent Constr. Notice - Doyle Park - Spanish
Imminent Constr. Notice - Juilliard Park
Imminent Constr. Notice - Juilliard Park - Spanish
Imminent Constr. Notice - Lakeville Hwy
Imminent Constr. Notice - Lakeville Hwy - Spanish
Imminent Constr. Notice - Roseland Creek Park
Imminent Constr. Notice - Roseland Creek Park - Spanish
Imminent Constr. Notice - Walker & Meadow Ave
Imminent Constr. Notice - Walker & Meadow Ave - Spanish

Other Information:
C02162 Invitation for Bids (for information only-see PlanetBids for bidding
C02162 Bid Results
Click for larger image
Project Image

Note: All dates and times are subject to change.