Capital Improvement Projects List

Image NOTE: The list of public facilities improvement projects shown below contains projects that have completed the necessary budgetary and environmental approval process, as well as those proposed for construction. Appearance of a project on this list does not constitute final approval of any project. Each project is subject to environmental and engineering review to be conducted in accordance with the applicable requirements of the California Environmental Quality Act (CEQA), and City Code provisions. To find out about a few Recreation & Parks projects not listed here, visit www.srcity.org/parks.

Click a Project ID in the table below to see the project web-page report.

Filtered by Projects with Paving Component

Down arrow imageClick a column header to turn on sorting. Year/Month.
StatusProjIDTitleDescriptionEst StartEst End
Image
Proposed
00544Laguna Treatment Plant Flood ProtectionThis project will install flood protection facilities for the Laguna Treatment Plant (LTP), the Geysers and Reclamation Pump Stations, and Biosolids facility. The overall flood protection system will include elevating portions of Llano Road, installing a passively activated floodgate across Llano Road, and installing earthen berms at strategic locations adjacent to the LTP at heights compliant with FEMA requirements.2026/072027/10
Image
Construction
00720Hearn Ave at Highway 101 - Phase 3 Rebuild InterchangeThe US 101 Hearn Avenue Regional Multimodal Interchange Project (project) will demolish and reconstruct the Hearn Ave interchange overcrossing in the same location to increase vertical clearance over United States Highway (US) 101, widen the overcrossing to provide two vehicle lanes in each direction, a median, sidewalks, and Class II and Class IV bikeways that will extend to Corby Avenue and Santa Rosa Avenue. The project will also widen the southbound US 101 off-ramp with turning lanes at its intersection with Corby Avenue, add lanes at the intersections of Hearn Avenue/Corby Avenue and Hearn Avenue/Santa Rosa Avenue, and add pedestrian curb ramps and crosswalks that meet the requirements of the ADA and incorporate protection and detection to reduce conflicts between bikes and vehicles.2024/052025/12
Image
Proposed
01178Fulton Rd from Guerneville Rd to Piner Rd - Widen to Four LanesThe purpose of this project is to ease future traffic congestion. Fulton Road will be reconstructed and widened to 4 lanes with bike lanes and sidewalks between Guerneville Road and Piner Road. The Project includes PG&E Rule 20A underground district, roller compact paving, 2 travel lines in each direction, widen sidewalk, bike lanes, median islands and storm drain improvements.2022/042024/12
Image
Proposed
01904Los Alamos Trunk Replacement: Elaine Dr to Melita Rd at Santa Rosa CreekThe purpose of this project is to replace an outdated and undersized section of the Los Alamos Sewer Trunk, which runs north of and parallel to Santa Rosa Creek from Elaine Drive to Melita Road. This project will provide trunk capacity, increase reliability and reduce maintenance. Relocation of the water main to create adequate separation from proposed sewer line is anticipated.N/AN/A
Image
Proposed
02212Tank Seismic Upgrades Phase 5 - R9A & R16 and Pump Station Improvements - S16 & S17Reservoir 9A was erected in 1977 & Reservoir 16 in 1994. West Yost Associates completed a safety, security, & code evaluation on the reservoirs. To bring up to code improvements were recommended. The scope of work incl. improvements to the tank foundations (incl. foundation reinforcing steel & additional anchorage embedment), additional shell courses raising the R16 roof by approximately 5' 9" & R9A roof by approx 8'-11", replacement of the interior center support columns, removal & replacement of interior & exterior coatings (changing exterior color from dark green to tan), and lighting (incl. exterior lighting) & electrical improvements. Water pump stations S16 & S17 will add 1,500 gpm high-flow pumps, VFDs, & building upgrades to improve firefighting capabilities and redundancy.2026/072028/11
Image
Proposed
022392017 Fire Damaged Roadway RepairsRepair Tubbs Fire pavement damage within the following roadway corridors. 1) Bicentennial Way - Cleveland Ave to Fountaingrove Pkwy On-ramp 2) Fountaingrove Pkwy - Mendocino Ave to Daybreak Ct2026/032026/11
Image
Proposed
02263Calistoga Road Pavement Rehabilitation & Utility Improvements - Montecito Boulevard to Highway 12The Calistoga Road Reconstruction project will rehabilitate approximately 1.1 center line miles of Calistoga Road using a combination of Full Depth Reclamation and mill and fill paving methodologies to address failing and deteriorating pavement conditions. Associated improvements will include adding buffered and protected bike lanes in select locations while maintaining existing Class II bike lanes in all other locations, updated bus stop infrastructure, and upgrading pedestrian curb ramps to current ADA standards. In addition to the roadway rehabilitation work, the project will include select water and sewer system infrastructure improvements on the order of approximately 4,850 LF of water pipe replacement/upsizing and 1,500 LF of sewer pipe replacement.2026/052027/07
Image
Proposed
02264B St High Traffic Slurry- 1st St to 7th StThe project will install a high traffic slurry over 1,800 linear feet of road way within the project limits and remove and replace the existing brick paver crosswalks with stamped and colored asphalt concrete. This project will also update out of compliance curb ramps to current ADA standards.N/AN/A
Image
Proposed
02406Hopper Ave Corridor Fire Recovery ImprovementsThis project will rehabilitate the Hopper Ave corridor between Coffey Ln and the Hwy 101 on ramp as a result of the damage caused by the 2017 Tubbs Fire. Improvements will include the addition of bike lanes, medians, landscape, pedestrian crossings, bulb outs a HAWK signal, utility realignment, sidewalk improvements, and new striping. Visit www.SRCity.org/EnvisionHopper for additional project details.2026/052027/02
Image
Proposed
02408B St and 3rd St SB Right Hand Turn Pocket ImprovementsThis project is slated to construct a right hand turn pocket lane in the south bound direction of B Street approaching the 3rd Street intersection. The project will include grading and relocation of utilities within the pocket area, relocation of a traffic pole, and relocation of the curb/gutter, sidewalk, and curb ramp.N/AN/A
Image
Construction
02508Roseland Pavement Maintenance - 2025This project will rehabilitate various streets within the 2017 Roseland annexation area.N/AN/A

Santa Rosa City Hall - 100 Santa Rosa Avenue - Santa Rosa, CA 95404