Capital Improvement Projects List

Image NOTE: The list of public facilities improvement projects shown below contains projects that have completed the necessary budgetary and environmental approval process, as well as those proposed for construction. Appearance of a project on this list does not constitute final approval of any project. Each project is subject to environmental and engineering review to be conducted in accordance with the applicable requirements of the California Environmental Quality Act (CEQA), and City Code provisions. To find out about a few Recreation & Parks projects not listed here, visit www.srcity.org/parks.

Click a Project ID in the table below to see the project web-page report.

Down arrow imageClick a column header to turn on sorting. Year/Month.
StatusProjIDTitleDescriptionEst StartEst End
Image
Proposed
00080Emergency Groundwater Supply DevelopmentThis is a multi-year project to locate and construct multiple groundwater wells to provide a backup water supply in the event of a natural disaster or other event that disrupts the City's water supply from the Sonoma County Water Agency.2014/012029/01
Image
Proposed
00158North Trunk Sewer Replacement - Mendocino Ave to Terra Linda DrThis project will address the existing lack of accessibility to the North Trunk Sewer main for routine maintenance and subject to risks associated with traversing adjacent and/or under an existing watercourse. The project will relocate the existing 1,650 ft. of 12 inch to 15 inch vitrified clay pipe (VCP) sewer main located adjacent to Paulin Creek.2020/022020/11
Image
Proposed
00227Fulton Rd Lift StationThis project funds the project environmental phase for the replacement/relocation of the existing West College Lift Station to the southwest corner of the Church property, located at the intersection of Fulton Road and West College Avenue. A technical memoradum prepared by Brown and Caldwell dated March 4, 2015 summarizes the interim improvements, remaining life of lift station, and recommends construction of a new lift station in approximately 15 to 20 years.2020/022020/11
Image
Proposed
00284Laguna Treatment Plant Ultraviolet Disinfection ReplacementPROJECT IS ON HOLD Due to recent regulatory changes, the existing UV system needs augmentation in order to meet capacity requirements during peak wet weather flows. The purpose of the Request for Proposal (RFP) is to accept qualifications and proposals from interested parties seeking to furnish all components required to provide a complete operable Low Pressure, High Output Ultraviolet Disinfection Equipment Systems for the City of Santa Rosa's (CITY) Laguna Treatment Plant. This RFP will provide the means to select a System, establish and hold pricing through a Memorandum of Understanding for the selected System that will allow CITY to brand name specify the System in a construction contract.2020/022020/11
Image
Proposed
00491R9C Tank Decommission and DemolitionReservoir R9C (formerly known as R9A) is located at 4788 Bennett Valley Road. This tank is past its design life, and was replaced by the new R9A & R9B tanks. Tank was disconnected from distribution network at intersection of Bennett Valley Road at Yulupa Road in 2104. Pipeline to the tank also needs to be capped at both ends at time of tank removal, hopefully both in 2015.2019/092020/01
Image
Proposed
00544Laguna Treatment Plant Flood ProtectionThis project will install flood protection facilities for the Laguna Treatment Plant, the Geysers and Reclamation Pump Stations, and Biosolids facility. The flood protection may include walls and berms as recommended in the "Flood Protection at the Laguna Treatment Plant Feasibility Study" that was completed in July, 2016.2020/082022/10
Image
Construction
00568Seismic Upgrades and Improvements Phase 4 - R3, R7 & R12B And Various Other Site Improvements - S1, S2, R6 & R12AThis project involves seismic retrofits and structural improvement upgrades to water reservoirs (R3, R7, R12B) to meet current seismic safety codes and requirements. In addition, site improvements addressing site security at R12A and minor drainage and accessibility concerns are proposed at each site, as well as coating improvements to the roof of water reservoir R6.2017/082019/07
Image
Proposed
00661Pacific Ave Reconstruction - Humboldt St to Montecito AveTo reconstruct Pacific Avenue between Humboldt Street and Montecito Avenue. The project will also include: - Curb ramps will be reconstructed at all intersections to meet current accessibility standards. -Replacement of a short section of sewer main as well as a section of the water main. -Replacement of water services and hydrants -Drainage inprovements -Rectangular Rapid Flashing Beacon (RRFB) systems at King Street and Elizabeth Way/Spring Street intersection. -Video Detection System at Humboldt Street, North Street and McDonald Avenue.2020/062021/06
Image
Construction
00685Garage 9 - Hazardous Materials (Investigation)This project is a Regional Water Quality Control Board mandated soil and groundwater study and remediation of petroleum contamination under the multi story parking garage.2018/082018/12
Image
Proposed
00720Hearn Ave at Highway 101 - Phase 3 Rebuild InterchangeThe existing Hearn Avenue interchange at Highway 101 will be rebuilt to ease traffic congestion and improve clearance over the highway. Improvements to the overpass and approaches will include widening to four vehicle lanes, with bike lanes and sidewalk on both sides.2020/082022/07
Image
Construction
00727Stony Point Road Widening and Reconstruction Phase 2 - Sebastopol Road to Hearn AveThe purpose of this project will be to ease traffic congestion by widening Stony Point Road to four lanes from Hearn Avenue to Sebastopol Road. The addition of travel and turn lanes, new sidewalks, bicycle lanes, and updated traffic signal upgrades will increase road safety along this vital north-south corridor. The project also includes the installation of new water main and water services, sewer main stubs to currently undeveloped parcels and storm drains.2015/082018/10
Image
Proposed
00769Highway 101 Bike/Pedestrian OvercrossingA pedestrian and bicycle bridge crossing over U.S. 101 will connect the northern half of Santa Rosa to residential, commercial, and academic institutions while providing safe and unimpeded bicycle access from high vehicular volumes at the U.S. 101 interchanges.2021/012022/07
Image
Proposed
00779Franklin Avenue Pedestrian PathConstruct a sidewalk on the west side of Franklin Avenue between Monroe Avenue and Terrace Way. A pedestrian crossing from Terrace Way across Franklin Avenue will be installed along with ADA ramp upgrades.2019/052019/06
Image
Construction
00780Fulton Rd Reconstruction - Occidental Rd to W 3rd StThis project will reconstruct Fulton Rd. between Occidental Rd. and W. 3rd St. using roller compacted concrete technology, replace deteriorated storm drain pipe near Darla Drive, install a new sewer manhole and update pedestrian ramps to current ADA standards. Roller compacted concrete has the benefit of reduced costs and longer service life. This project will improve safety and reduce ongoing maintenance costs.2019/062019/10
Image
Construction
01133Cooper Drive Slope Stabilization and Drainage ImprovementsThis project consists of replacing approximately 750 feet of deteriorated concrete lined drainage ditch at the rear of properties located along the east side of Cooper Dr. Retaining wall and subdrainage improvements will be installed support drainage improvements.2019/062019/12
Image
Proposed
01178Fulton Rd from Guerneville Rd to Piner Rd - Widen to Four LanesThe purpose of this project is to ease future traffic congestion. Fulton Road will be reconstructed and widened to 4 lanes with bike lanes and sidewalks between Guerneville Road and Piner Road. The project includes PG&E Rule 20A underground district, a median island and storm drain improvements.2020/072022/02
Image
Proposed
01549Inspection of Bridge Assets: Structural CrossingsContinuous maintenance work and assessments on various pedestrian bridges and culverts throughout the City.2020/072022/02
Image
Construction
01568Grosse Ave, El Camino Way, and Augustan Ave Sewer and Water Replacement - Dowling Ct to East Haven DrThis project will replace sewer and water mains in Augustan Avenue, El Camino Way from Grosse Avenue to Augustan Avenue, and in Grosse Avenue from El Camino Way to Dowling Court. This project will abandon an inaccessible backyard easement and re-plumb the tributary lots to the public sewer in the street. Ten pedestrian ramps will be replaced. All streets will be reconstructed.2019/052020/05
Image
Construction
01582Elizabeth Way Sewer and Water ReplacementThis project is part of the replacement of the Grace neighborhood water and sewer mains. This project will replace undersized and aged water main and aged and obsolete sewer main in Elizabeth Way from Parsons Drive to Town and Country Drive. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing older deteriorated VCP pipe reduces inflow and infiltration and reduces maintenance costs. Pavement will be reconstructed.2018/092019/01
Image
Proposed
01675Montgomery Dr Water Replacement - Mission Blvd to Jackson DrThis project will replace a parallel 4" steel water (1947) main and a 6" ACP water main (1969) with a single 8" water main from Montgomery Drive and from Mission Boulevard to Jackson Drive. The 4" steel main is of primary concern and a new single main will reduce maintenance costs.2020/082020/10
Image
Proposed
01727SMART Hearn Avenue Multi Use Path CrossingThis project will design and install a signalized crosswalk at the SMART multi-use path intersecting with Hearn Avenue. The crosswalk will be installed on the east side of the track and will require that a portion of the median island be removed to accommodate the crosswalk. The crosswalk will be illuminated and will be connected to the railroad equipment in order to turn red in conjunction with the railroad crossing activation.2019/092020/05
Image
Proposed
01801R7 Road Access Stabilization RepairsThe purpose of this project is to provide soil and slope stability improvements along the access road to water storage tank R7 and provide drainage improvements from the tank site to St. Francis Road.2019/062019/08
Image
Construction
01839Farmers Ln Well Facility RehabilitationThe Farmers Lane Wells and Treatment Plant needs rehabilitation to restore the wells production capacity. This project focuses on the needed rehabilitation for the well facilities with a separate project to focus on the treatment plant rehabilitation in FY 18/19. The work to be completed for rehabilitating the wells includes replacing the existing pumps with a submersible pump at W4-1 and a vertical in-line pump at W4-2; installing new electrical service; and replacing/expanding the buildings to house the new electrical components on-site.2017/102019/03
Image
Proposed
01899Guerneville Rd Pedestrian PathThis project will build pedestrian paths or sidewalks to close existing sidewalk gaps on the north side of Guerneville Road between Ridley Avenue and Marlow Road.2019/082019/10
Image
Proposed
01903Los Alamos Trunk Replacement: Streamside Dr to Elaine DrThis project includes providing the preliminary design and supporting studies for replacement of the existing Los Alamos sewer trunk from Streamside Drive to Melita Drive (approximately 16,000 linear feet (LF)). Construction documents will be prepared for the downstream segment (approximately 5,500 LF) from Streamside Drive to Elaine Drive. The trunk, installed in the 1950's is undersized and is in poor condition. This project will provide more capacity to help prevent overflows, increase reliability, and reduce maintenance. In addition, it will be re-aligned out of yards and further away from the creek where practical. Relocation of the water main may be necessary in certain locations to create adequate separation from proposed sewer line.2020/072022/01
Image
Proposed
01904Los Alamos Trunk Replacement: Elaine Dr to Melita Rd at Santa Rosa CreekThe purpose of this project is to replace an outdated and undersized section of the Los Alamos Sewer Trunk, which runs north of and parallel to Santa Rosa Creek from Elaine Drive to Melita Road. This project will provide trunk capacity, increase reliability and reduce maintenance. Relocation of the water main to create adequate separation from proposed sewer line is anticipated.2022/042024/04
Image
Construction
01909Northerly Slope Protection Ponds C & D and Pond B Slope RepairThe northerly slopes of reclaimed water Ponds C and D need protection from further erosion created by wave action from storm events. In addition, the westerly slope of Pond B suffered a slope failure during the winter of 2018-2019 and needs repair.2019/072021/10
Image
Proposed
01924Lower Colgan Creek Restoration - Phase 2This restoration project will restore 2,170 lineal feet of straightened and denuded channel into a natural creek while still providing flood protection. This project is the second phase of a three phase project. The new alignment will allow the creek channel to have greater water retention during high flows. There will be in-stream structures and pools installed to enhance aquatic life such as boulders, boulder weirs, and over 1,000 native trees, shrubs and grasses. Project limits are from Victoria Drive downstream to Boron Avenue.2020/062020/10
Image
Proposed
01943Vallejo Street Trunk Sewer Junction Structure ModificationsThe sewer junction structure for the Crosstown and Bennett Valley Trunks has only one access point for maintenance at the incoming line on the Crosstown Trunk but not on the incoming Bennett Valley Trunk nor on the outgoing combined flow trunk. The additional two access points in the junction structure will greatly improve visual inspections and facilitate cleaning and maintenance for the entire junction structure and connecting trunk mains.2017/102018/08
Image
Warranty
01996E St Sewer Replacement - 2nd St to Santa Rosa CreekThis project replaces aged and deteriorated clay sanitary sewer main to reduce maintenance needs as well as inflow and infiltration. The new sewer main will also be extended to eliminate issues associated with a lateral that is prone to clogging in the public right of way.2018/112019/01
Image
Proposed
01999Cobblestone Dr Zone R2-R4 Water Main ConnectionThis project is meant to improve fire protection water flow in the Cobblestone neighborhood only. No new water service connections are incluced. Several fire hydrants serving approximately 32 homes at the north end of Cobblestone Dr have sub-optimal fire flow ranging from approximately 752 gpm at 20 psi to 1329 gpm at 20 psi. A new 8" pipeline is proposed to connect the existing pipeline in Tillmont Way (located in the City's Pressure Zone R2) to the existing 6-inch diameter pipeline located in Cobblestone Drive (located in Pressure Zone R4).2020/022020/11
Image
Construction
02003Donahue, Decker, Boyce & Petaluma Hill Sewer and Water Main ImprovementsThis project will remove and replace approximately 500 feet of aged and deteriorated vitrified clay sewer mains and laterals in Donahue, Becker and Boyce Streets, and replace approximately 130 feet of aged and undersized water mains in Decker St. This project will also replace approx. 785 feet of aged and deteriorated sewer main and laterals in Petaluma Hill Rd. A total of 18 curb ramps will also be upgraded to the curent ADA standards.2019/062019/12
Image
Construction
02004Alvarado Ave and Vallejo St Water and Sewer ImprovementsPhase I will upsize water and sewer mains on Alvarado Avenue and the water main on Vallejo Street between Mt. Olive Drive and Melbrook Way to meet fire flow requirements as identified in the 2014 Water Master Plan. Phase II will improve the sewer junction structure for the Crosstown and Bennett Valley Trunk mains. Two access points will be added to the junction structure to improve visual inspections and facilitate cleaning and maintenance for the entire junction structure and connecting trunk mains.2018/092019/08
Image
Proposed
02041Cleveland Ave and 7th Street Lateral Installation and Sewer Main AbandonmentThis project will abandon approximately 700 feet of clay sewer main on the west side of Cleveland between Ridgway Avenue and Carrillo Street by transferring 23 laterals to an existing PVC sewer trunk on the east side of Cleveland Avenue. Additionally, this project will include sewer system improvements for 7th Street and B Street. The work on 7th Street will abandon 540 feet of clay sewer main and transfer 2 laterals to an existing sewer trunk between A Street and B Street. The work on B Street includes replacing a 30-foot section of deteriorated pipe near Healdsburg Avenue. This work will reduce inflow and infiltration and reduce maintenance costs.2018/092019/08
Image
Construction
02042Llano Trunk Lining - W College Utilities FacilityThis project will rehabilitate approximately 1,100 feet of pipeline by cured-in-place pipe (CIPP) lining inserted into the existing sewer main pipe, located within the W. College Utilities Facility. Six manholes will be rehabilitated a corrosion resistant epoxy liner for protection against future hydrogen sulfide deterioration.2019/082020/10
Image
Construction
02051Laguna Treatment Plant Primary Influent Pump Drive ReplacementThis project will replace all 6 primary influent pump drives which are critically important for operation of the Laguna Treatment Plant and are now obsolete.2019/082020/10
Image
Proposed
02058 Alderbrook Drive Crossing TreatmentConstruct two pedestrian ramps (one a possible bulb out) and pedestrian median refuge island at Fourth Street and Alderbrook on the west leg of the intersection.2019/082020/10
Image
Construction
02059Mendocino Ave and McConnell Ave Intersection Pedestrian ImprovementsConvert the Pedestrian Activated Flasher to a Pedestrian Hybrid Beacon at the intersection of Mendocino Avenue and McConnell Avenue. This would include prohibiting lefts from McConnell westbound to southbound Mendocino Avenue per the corridor plan.2019/032019/05
Image
Construction
02079Farmers Lane Well Facility Pump Replacement ProjectIn order to meet the proposed construction schedule for the Farmers Lane Well Rehabilitation Project, the well pumps will need to be pre-purchased due to the long lead time. A submersible pump is planned to be installed in W4-1 with a nominal pumping capacity of about 840 gpm. A vertical turbine pump is planned to be installed in W4-2 with a nominal capacity of about 1,660 gpm, providing a total capacity of 2,500 gpm.2017/102019/03
Image
Proposed
02083Emergency Groundwater Wells at Oakmont Treatment Plant and Speers RdThis project is intended to provide the City of Santa Rosa with two investigative boreholes, on two different parcels in Northeast Santa Rosa, to evaluate the viability of installing emergency wells or monitoring wells. This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water's Groundwater website located at: http://ci.santa-rosa.ca.us/857/Groundwater2017/102019/03
Image
Proposed
02091Flashing Yellow Left Turn Arrow RetrofitRetrofit and upgrade thirty-nine (39) Protected/Permissive signalized intersections with Flashing Yellow Left Turn Arrow displays to meet current standards.2017/102019/03
Image
Construction
02101Laguna Treatment Plant Digester Gas Conditioning ImprovementsDigester gas flows to the CHP facility have increased since the commissioning of the High Strength Waste facility. The increased gas flows have shown a need to improve/upgrade certain components of the Plant digester gas conditioning equipment. Design requirements as determined by engineering consultant will be required.2018/122019/07
Image
Construction
02113Roseland Pavement MaintenanceTo share in the City's transportation infrastructure costs for the Roseland annexation, the County will provide funding of $6.62M over a 10-year period (Transportation Payment") to cover pavement improvement costs in the Roseland annexation area which may include asphalt paved walkways on the shoulders and required ADA upgrades.2019/072019/09
Image
Proposed
02117S Fulton Trunk Sewer Repair - Fulton Rd at Santa Rosa CrkEliminate the constrictions in the existing sewer pipe across Santa Rosa Creek between manhole 12 and manhole 13. The existing 18-inch ACP sewer was installed in 1969 under the creek and west of the Fulton Road bridge. The 18-inch ACP sewer was lined with a 14-inch polyethylene (PE) liner in 1985. CCTV video indicates that the PE liner is deformed creating constrictions. Open-cut replacement with a new 8-inch diameter pipe was the method recommended by the consultants RMC/Woodward & Curran in their Technical Memorandum dated February 26, 2018. A cofferdam, fish relocation, and construction area creek flow bypass will likely be necessary.2020/082021/10
Image
Proposed
02131Accessibility Alterations at Howarth ParkRemove, grade and construct concrete pathways at Howarth park for the purpose of compliance with accessibility standards. The proposed area of alteration includes: 1) Alterations to the loading area at the train station for an accessible train car. 2) The area around the Carousel. 3) An accessible route to the animal barn and pony rides. 4) A ramp system through the picnic area by the carousel.2020/082021/10
Image
Proposed
02134Parking Lot 10 ReconstructionThis project will improve and extend the life of several parking lots using two different types of road surface sealing products, hot mix asphalt pavement, replacing trees, driveway approaches, planter strips and repairing sidewalks at six downtown parking lots.2020/082021/10
Image
Construction
02137Oakmont Dr. Sewer Main Upsizing Oakmont Creek to Greenfield CirReplace approximately 1188 feet of 6 inch ACP main with 10 inch PVC in Oakmont Drive (Oakmont Creek to Greenfield Circle) as this section is undersized and has resulted in two sanitary sewer overflows since 2009. Pedestrian ramps will be upgraded to current standards within the project limits.2019/042019/09
Image
Proposed
02146City Hall Campus Sidewalk ReconstructionThe project will upgrade sidewalk, driveways and curb ramps at the following locations: 90 Santa Rosa Ave (west side only), 100 Santa Rosa Ave (east, south and west sides only), 635 First Street (east side only), and Parking Garage 9 (D Street side only.) It will be completed in two phases. Phase One will include 90 Santa Rosa Ave (west side only), 635 First Street (east side only), and Parking Garage 9 (D Street side only.) PhaseTwo will include100 Santa Rosa Ave (east, south and west sides only.)2019/042019/09
Image
Construction
02150Station 2 Emergency Generator Replacement and Station 3 Power Filter InstallationThis project will install a filter to eliminate harmonic feedback to insure proper operation of the emergency generator at the Station 3 pump station. Additionally, this project will replace the existing emergency generator at Station 2.2019/042019/09
Image
Proposed
02162Building Demolition-Various City LocationsThe City owns numerous parcels with existing vacant/dilapidated structures within, and outside of, City limits. Many of these structures exist in locations that are slated for an alternative use and present a liability to the City if they were to remain in place. This project aims to demolish and clear the sites these structures occupy. The demolition of these structures will allow for expanded use of City property, increase the available land area for biosolid land application and add capacity to City owned parking lots. Locations: Doyle Park, Galvin Park, Julliard Park, Howarth Park, Roseland Creek Park, 2810 4th Street, 952 Sonoma Ave, 7630 & 7650 Lakeville Hwy., 4090 Walker Rd., 4099 Walker Rd., 1595 Meadow Ln.2019/082019/11
Image
Proposed
02182MSCN Stockpile Pad ReplacementThe Project will replace 6,600 square feet of existing asphalt surface with portland cement concrete paving in the MSCN Corporation Yard. The proposed replacement of a rectangular shaped pavement area fronts the existing stockpile bays where construction aggregate material is stored. This project will give City Maintenance Crews an improved durable pavement surface to work from and allow the loose aggregate materials, originating from material stockpiles, to be swept up and collected prior to any rain storm events. Construction is expected to start August 2019, and will last for approximately a month.2019/082019/09
Image
Proposed
02184Permanent Fire Station 5 RebuildClear debris and facilities damaged from the Tubbs fire and re-construct Fire Station 5.2021/072023/07
Image
Proposed
021862019 Pavement MarkingThis project is for the annual contract maintenance installation of edge lines, raised pavement markers, and bike lane lines throughout Santa Rosa. It is intended to ensure bicyclists remain within a bike pathway on the street system by highlighting travel lanes and bike lanes and to provide striping modifications to the street system as needed.2021/072023/07
Image
Proposed
02190Rehabilitate Matanzas SiphonsBoth the Matanzas and Glenbrook Siphons are in need of rehabilitation as determined by recent (Nov and Dec of 2017) televising of the siphon pipes. Both siphons where constructed in 1956 with the same construction techniques and materials.2019/102019/11
Image
Proposed
02198Bicycle and Pedestrian Gap Closures - Piner Rd and Dutton AveThe project has two locations. The first location will rehabilitate the outside lanes of pavement and provide bicycle lanes on Piner Road between Coffey Lane and Range Avenue. The second location will provide a sidewalk on the east side of Dutton Avenue just south of Jennings Avenue. Both locations will include upgrading the curb ramps to current standards.2019/092020/02
Image
Proposed
02201Skyfarm A and Hansford Lift Stations Reconstructions-Fire RelatedTwo lift stations were severely damage during the Tubbs Fire. One is located on SkyFarm Drive near Saint Andrews Drive and the other at the end of Hansford Court. They both must be reconstructed.2019/102020/10
Image
Proposed
02204EGW Freeway WellThe purpose of this project is to implement the City's Groundwater Master Plan by utilizing a State grant and local matching funds to evaluate known and potential water quality risks in the vicinity of the Freeway Well and study the feasibility of groundwater cleanup, protection, and/or development (to replace Freeway Well in kind) to ensure adequate emergency water supply, particularly for the northeast area of Santa Rosa. This project will examine the area around the Freeway Well to more fully characterize the groundwater contamination problem, better understand the lithology and deep aquifer hydrology, and provide additional groundwater sampling and data analysis.2019/092019/11
Image
Proposed
02208Fire-Related Repairs of Utility StationsSeveral potable water stations, reservoirs and sewer lift stations sustained damage during the Tubbs Fire. This project will undertake rehabilitation efforts at the affected sites.2019/092020/06
Image
Construction
02213Replacement of Water Services Outside Advisory AreaThis project will remove and replace the water services damaged by the Tubbs Fire with new 1 in. Polyvinyl Copper Services from the water main to the meter to properties located outside the Advisory Area.2018/062019/03
Image
Proposed
02221Pavement Rehabilitation for City Parking Lots 7 and 11This project will rehabilitate distressed pavement surfaces at City Parking Lots 7 and 11 by using multiple pavement rejuvenation applications such as slurry seal, scrub seal and skin patch. Approximate total surface area of both lots is 90,000 SF.2018/062019/03
Image
Warranty
02222Replacement of Water Services Inside Advisory AreaThis project will remove and replace the water services damaged by the Tubbs Fire with new 1 in. Polyvinyl Copper Services from the water main to the meter to properties located inside the Advisory Area.2018/062018/10
Image
Proposed
02223Installation of Public Restroom in Downtown AreaInstallation of one (1) restroom kiosk in Downtown Santa Rosa area, specific location to be determined.2020/042020/05
Image
Proposed
02227Fire Damage Storm Drain Repairs- CitywideThis project will repair fire damaged storm drain drop inlets at 18 locations.2019/052019/06
Image
Construction
02229Fire Damage-Related Repairs to Three Pedestrian BridgesRepair three fire-damaged pedestrian bridges: 1) Francis Nielsen Park Bridge, 35' x 6' foot wide wooden pedestrian bridge 2) Parker Hill Road Bridge north, 40' x 7' steel pedestrian bridge with wooden deck 3) Parker Hill Road Bridge south, 40' x 7' steel pedestrian bridge with wooden deck2019/062019/09
Image
Proposed
02233Fire Related Street Light ReplacementThis project will replace 181 fire damaged street lights in the Coffey Park area.2020/012020/04
Image
Proposed
02234Samuel Jones Hall, Water Station 4 and 13 Roof ReplacementsRoof Replacement at Sam Jones Hall (4020 Finley Ave.) Water Pump Station 4 (2260 Sonoma Ave.) And Water Pump Station 13 (801 White Oak Dr.) Work will also include rooftop HVAC replacement at Sam Jones Hall per a 2018 Facilities Condition Assessment.2019/082019/11
Image
Construction
02240Minor Work for Water Services Affected by the Tubbs Fire - Cat FApproximately 71 contaminated water service lines at 54 locations were replaced by the Water Department outside of the advisory area in the spring of 2018. The Contractor will return to those locations to perform some additional work that could not be performed by City Crews. The Contractor will replace the existing meter box in kind and install 1 in. Polyethylene coated copper tubing to approximately 12 in. behind the sidewalk to connect to in the future. The contractor will also be replacing the sidewalk at this location. If there is no existing sidewalk, the 1 in. Polyethylene coated copper will be extended to approximately 12 in. beyond the water meter box.2019/062019/08
Image
Proposed
02245Asphalt Spot Repairs of Actual Burned AreasThis project will repair the burned asphalt concrete pavement in the Coffey Park and Fountaingrove areas.2020/062020/08
Image
Proposed
02246Replace 314 Street Lights in FountaingroveThis project will replace 314 street lights caused by the fire related damage in the Fountaingrove area.2019/112020/04
Image
Proposed
02247Cross Creek Vehicle Bridge Fence RepairThis project will replaced the fence above the culvert on Cross Creek Rd at Ribeli Creek on upstream side as the result from the fire damage.2019/112020/04
Image
Construction
02251Annual Slurry Seal 2019This project will apply slurry seal to various (primarily residential) City streets. Streets are slurried by applying a thin, quarter-inch roadway coating of liquid asphalt and sand. Slurry seal restores the pavement's ability to prevent water intrusion, corrects minor cracking and improves skid resistance. Priorities are established by the Pavement Management System.2019/072019/08
Image
Proposed
02252Pavement Preventive Maintenance 2019This project will consist of performing preventive maintenance on City streets by contract. Work to be completed is crack sealing, asphalt dig outs, and pavement resurfacing2019/082019/09
Image
Construction
02254Stony Point Rd Utility Box Adjustments and Sidewalk RepairsComplete sidewalk gap closures and utility box adjustments.2019/082019/09
Image
Construction
02260Removal of Fire-Damaged Hazardous Street TreesThe City contracted a certified arborist to perform a field survey of all street trees (those in the public right-of-way) in the areas affected by the fires. The Arborist Report identified approximately 700 street trees as being a potential hazard and recommended for removal. Beginning late June through October 2019, a contractor will begin removal of hazardous fire-damaged street trees in the burn scar areas, which will include grinding of the tree stumps and filling the planter strips with fresh soil. The trees to be removed will be identified by a red mark on their trunks. Project work hours will be 8:30 a.m. to 4:00 p.m., Monday Friday.2019/062019/10
Image
Proposed
02269Santa Rosa Consolidation ProjectThe scope of this project is to connect nine community water systems to City water. This project is Prop 84 funded. The nine Locations are listed below: - El Crystal Mobile Estates - Mountain View Mobile Estates - Roseland Mobile Home Park - James Court - Delores Lane - Wayside Gardens Mobile Home Park - El Portal Mobile Estates - Plaza Mobile Home Park - Western Mobile Home Park2020/102021/03

Santa Rosa City Hall - 100 Santa Rosa Avenue - Santa Rosa, CA 95404