Capital Improvement Projects List

Image NOTE: The list of public facilities improvement projects shown below contains projects that have completed the necessary budgetary and environmental approval process, as well as those proposed for construction. Appearance of a project on this list does not constitute final approval of any project. Each project is subject to environmental and engineering review to be conducted in accordance with the applicable requirements of the California Environmental Quality Act (CEQA), and City Code provisions. To find out about a few Recreation & Parks projects not listed here, visit www.srcity.org/parks.

Click a Project ID in the table below to see the project web-page report.

Down arrow imageClick a column header to turn on sorting. Year/Month.
StatusProjIDTitleDescriptionEst StartEst End
Image
Proposed
00080Emergency Groundwater Supply DevelopmentThis is a multi-year project to locate and construct multiple groundwater wells to provide a backup water supply in the event of a natural disaster or other event that disrupts the City's water supply from Sonoma Water.2014/012029/01
Image
Proposed
00158North Trunk Sewer Replacement - Mendocino Ave to Terra Linda DrThis project will address the existing lack of accessibility to the North Trunk Sewer main for routine maintenance and subject to risks associated with traversing adjacent and/or under an existing watercourse. The project will relocate the existing 1,650 ft. of 12 inch to 15 inch vitrified clay pipe (VCP) sewer main located adjacent to Paulin Creek.2020/082021/10
Image
Proposed
00284Laguna Treatment Plant Ultraviolet Disinfection ReplacementUltraviolet light (UV) is the primary disinfection process for the City of Santa Rosa's Laguna Treatment Plant (LTP). The existing system was commissioned in 1998, has reached the end of its useful life, and no longer has the treatment capacity for peak wet weather sewer flows. This project will replace the existing UV system with a new UV system. Additionally, this project will install an effluent diversion pump station and pipeline to convey effluent to the beginning of the plant for retreatment. This provides greater flexibility for operations and regulatory compliance.2021/062022/11
Image
Proposed
00308La Paloma Ave / East Haven Dr / Rogers Wy Sewer and Water Main ReplacementThis project is one phase of the replacement of Grace neighborhood water and sewer mains. Sewer and water mains replacements planned for this phase of work include: East Haven Dr from 4th St to Eleanor, La Paloma Ave from East Haven Dr to Rogers Way, and Rogers Way from La Paloma Ave to 4th St. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing sewer main pipe reduces inflow and infiltration and also reduces maintenance costs. All streets will be reconstructed and minor stormdrain and pedestrian ramp improvements will be made at the intersection of East Haven Dr and La Palomoa Ave.2020/062020/11
Image
Proposed
00491R9C Tank Decommission and DemolitionReservoir R9C (formerly known as R9A) is located at 4788 Bennett Valley Road. This tank is past its design life, and was replaced by the new R9A & R9B tanks. Tank was disconnected from distribution network at intersection of Bennett Valley Road at Yulupa Road in 2014. Decommissioned tank will be demolished, the pipeline to the tank will also be capped at both ends at the time of tank removal and the site will be restored to pre-development conditions.2020/052020/07
Image
Proposed
00544Laguna Treatment Plant Flood ProtectionThis project will install flood protection facilities for the Laguna Treatment Plant, the Geysers and Reclamation Pump Stations, and Biosolids facility. The flood protection may include walls and berms as recommended in the "Flood Protection at the Laguna Treatment Plant Feasibility Study" that was completed in July, 2016.2021/092023/09
Image
Proposed
00661Pacific Ave Reconstruction - Humboldt St to Montecito AveTo reconstruct Pacific Avenue between Humboldt Street and Montecito Avenue. The project will also include: - Curb ramps will be reconstructed at all intersections to meet current accessibility standards. -Replacement of a short section of sewer main on Pacific Avenue and a sewer main supporting 1320 North Street as well as a large section of the water main. -Replacement of water services and hydrants -Drainage inprovements -Rectangular Rapid Flashing Beacon (RRFB) systems at King Street, Beaver Street and Elizabeth Way/Spring Street intersection. -Video Detection System at Humboldt Street, North Street and McDonald Avenue.2020/092021/06
Image
Proposed
00685Garage 9 - Hazardous Materials (Investigation)This project is a Regional Water Quality Control Board mandated soil and groundwater study and remediation of petroleum contamination under the multi story parking garage.2019/122020/08
Image
Construction
00700Sidewalk Survey and MaintenanceThis project will survey the Downtown & Railroad Square business districts and repair minor sidewalk lifts utilizing a horizontal saw cutting method. Based on the amount of repairs required from the survey and the funding provided to the project, the surveyed area has been mapped and is larger than the repair area under this contract. Priorities were discussed with the Planning department and the Santa Rosa Downtown District Executive Director. This project is intended to benefit the community and goes above and beyond the City's responsibility to maintain sidewalk.2019/102019/12
Image
Proposed
00720Hearn Ave at Highway 101 - Phase 3 Rebuild InterchangeThe existing Hearn Avenue interchange at Highway 101 will be rebuilt to ease traffic congestion and improve clearance over the highway. Improvements to the overpass and approaches will include widening to four vehicle lanes, with bike lanes and sidewalk on both sides.2021/012023/01
Image
Construction
00727Stony Point Road Widening and Reconstruction Phase 2 - Sebastopol Road to Hearn AveThe purpose of this project will be to ease traffic congestion by widening Stony Point Road to four lanes from Hearn Avenue to Sebastopol Road. The addition of travel and turn lanes, new sidewalks, bicycle lanes, and updated traffic signal upgrades will increase road safety along this vital north-south corridor. The project also includes the installation of new water main and water services, sewer main stubs to currently undeveloped parcels and storm drains.2015/082018/10
Image
Proposed
00769Highway 101 Bike/Pedestrian OvercrossingA pedestrian and bicycle bridge crossing over U.S. 101 will connect the northern half of Santa Rosa to residential, commercial, and academic institutions while providing safe and unimpeded bicycle access from high vehicular volumes at the U.S. 101 interchanges.2023/052024/05
Image
Construction
00780Fulton Rd Reconstruction - Occidental Rd to W 3rd StThis project will reconstruct Fulton Rd. between Occidental Rd. and W. 3rd St. using portland cement concrete technology, replace deteriorated storm drain pipe near Darla Drive, install a new sewer manhole and update pedestrian ramps to current ADA standards. This project will improve safety and reduce ongoing maintenance costs.2019/062020/02
Image
Proposed
01178Fulton Rd from Guerneville Rd to Piner Rd - Widen to Four LanesThe purpose of this project is to ease future traffic congestion. Fulton Road will be reconstructed and widened to 4 lanes with bike lanes and sidewalks between Guerneville Road and Piner Road. The project includes PG&E Rule 20A underground district, a median island and storm drain improvements.2021/062022/12
Image
Proposed
01539Hoen Ave Embankment RepairThe roadway within the southerly half of Hoen Avenue along the north side of Matanzas Creek between Brasher Court and Hoen Court has settled considerably. Deep polymer injection technology will be utilized to stabilize the roadway. The roadway within the project limits will be reconstructed upon stabilization.2020/042020/08
Image
Proposed
01549Inspection of Bridge Assets: Structural CrossingsContinuous maintenance work and assessments on various pedestrian bridges and culverts throughout the City.N/AN/A
Image
Construction
01568Grosse Ave, El Camino Way, and Augustan Ave Sewer and Water Replacement - Dowling Ct to East Haven DrThis project will replace sewer and water mains in Augustan Avenue, El Camino Way from Grosse Avenue to Augustan Avenue, and in Grosse Avenue from El Camino Way to Dowling Court. This project will abandon an inaccessible backyard easement and re-plumb the tributary lots to the public sewer in the street. Ten pedestrian ramps will be replaced. All streets will be reconstructed.2019/052020/05
Image
Proposed
01675Montgomery Dr Water Main Replacement - Mission Blvd to Jackson DrThis project will replace a parallel 4" steel water (1947) main and a 6" ACP water main (1969) with a single 8" water main from Montgomery Drive and from Mission Boulevard to Jackson Drive. The 4" steel main is of primary concern and a new single main will reduce maintenance costs.2020/062020/08
Image
Proposed
01727SMART Hearn Avenue Multi Use Path CrossingThis project will design and install a signalized crosswalk at the SMART multi-use path intersecting with Hearn Avenue. The crosswalk will be installed on the east side of the track and will require that a portion of the median island be removed to accommodate the crosswalk. The crosswalk will be illuminated and will be connected to the railroad equipment in order to turn red in conjunction with the railroad crossing activation.2020/082020/10
Image
Proposed
01801R7 Road Access Stabilization RepairsThe purpose of this project is to provide soil and slope stability improvements along the access road to water storage tank R7 and provide drainage improvements from the tank site to St. Francis Road.2020/042020/11
Image
Construction
01839Farmers Ln Well Facility RehabilitationThe Farmers Lane Wells and Treatment Plant needs rehabilitation to restore the wells production capacity. This project focuses on the needed rehabilitation for the well facilities with a separate project to focus on the treatment plant rehabilitation in FY 18/19. The work to be completed for rehabilitating the wells includes replacing the existing pumps with a submersible pump at W4-1 and a vertical in-line pump at W4-2; installing new electrical service; and replacing/expanding the buildings to house the new electrical components on-site.2017/102019/03
Image
Proposed
01899Guerneville Rd Pedestrian PathThis project will build pedestrian paths or sidewalks to close existing sidewalk gaps on the north side of Guerneville Road between Ridley Avenue and Marlow Road.2021/032021/06
Image
Proposed
01903Los Alamos Trunk Replacement: Streamside Dr to Elaine DrThis project includes providing the preliminary design and supporting studies for replacement of the existing Los Alamos sewer trunk from Streamside Drive to Melita Drive (approximately 16,000 linear feet (LF)). Construction documents will be prepared for the downstream segment (approximately 5,500 LF) from Streamside Drive to Elaine Drive. The trunk, installed in the 1950's is undersized and is in poor condition. This project will provide more capacity to help prevent overflows, increase reliability, and reduce maintenance. In addition, it will be re-aligned out of yards and further away from the creek where practical. Relocation of the water main may be necessary in certain locations to create adequate separation from proposed sewer line.2020/112022/01
Image
Proposed
01904Los Alamos Trunk Replacement: Elaine Dr to Melita Rd at Santa Rosa CreekThe purpose of this project is to replace an outdated and undersized section of the Los Alamos Sewer Trunk, which runs north of and parallel to Santa Rosa Creek from Elaine Drive to Melita Road. This project will provide trunk capacity, increase reliability and reduce maintenance. Relocation of the water main to create adequate separation from proposed sewer line is anticipated.2024/042025/08
Image
Proposed
01924Lower Colgan Creek Restoration - Phase 2This restoration project will restore 2,170 lineal feet of straightened and denuded channel into a natural creek while still providing flood protection. This project is the second phase of a three phase project. The new alignment will allow the creek channel to have greater water retention during high flows. There will be in-stream structures and pools installed to enhance aquatic life such as boulders, boulder weirs, and over 1,000 native trees, shrubs and grasses. Project limits are from Victoria Drive downstream to Boron Avenue.2020/052020/11
Image
Proposed
01929Reconstruct Pierce Street between 4th St and 3rd StReconstruct Pierce street between 4th st and 3rd st. Redesign Road conform with 4th Sreet, add curb ramps and drainage as needed. Scope to include water main replacement and upsizing.2021/022021/03
Image
Proposed
01965Emergency Well Pump Station- A Place to PlayThe purpose of this project is to convert the existing test well to an Emergency Groundwater Well, along with design and construction of a well pump station and appurtenances associated with the Emergency Groundwater Well at A Place to Play Park.This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water's Groundwater website located at: https://srcity.org/857/Groundwater.2020/062021/06
Image
Proposed
01994Pump Station 15 UpgradesThe purpose of this project is to perform upgrades to our water pumping facility in the Oakmont neighborhood. This project installs a higher energy efficient motor starter on the largest pump (VFD), replaces the emergency standby power generator, recoats the hydropneumatic tank, and replaces outdated controls and instrumentation equipment as part of the overall need to reduce maintenance and improve system reliability.2020/052021/04
Image
Proposed
02041Cleveland Ave and 7th Street Lateral Installation and Sewer Main AbandonmentThis project will abandon approximately 700 feet of clay sewer main on the west side of Cleveland between Ridgway Avenue and Carrillo Street by transferring 23 laterals to an existing PVC sewer trunk on the east side of Cleveland Avenue. Additionally, this project will include sewer system improvements for 7th Street and B Street. The work on 7th Street will abandon 540 feet of clay sewer main and transfer 2 laterals to an existing sewer trunk between A Street and B Street. The work on B Street includes replacing a 30-foot section of deteriorated pipe near Healdsburg Avenue. This work will reduce inflow and infiltration and reduce maintenance costs.2020/062020/11
Image
Construction
02058 Alderbrook Drive Crossing TreatmentConstruct two pedestrian ramps (one a possible bulb out) and pedestrian median refuge island at Fourth Street and Alderbrook on the west leg of the intersection.2020/042020/05
Image
Proposed
02083Emergency Groundwater Wells at Oakmont Treatment Plant and Speers RdThis project is intended to provide the City of Santa Rosa with two investigative boreholes, on two different parcels in Northeast Santa Rosa, to evaluate the viability of installing emergency wells or monitoring wells. This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water's Groundwater website located at: http://ci.santa-rosa.ca.us/857/GroundwaterN/AN/A
Image
Proposed
02090Class II Bike Lane Gap ClosuresProject will close gaps in the Class II bicycle lane on Piner Road between Marlow Road and Coffey Lane, W. Third Street between Stony Point Road and Brittain Lane and Hopper Avenue between Coffey Lane and Airway Drive. The project will restripe segments and design will ensure that changes made will have minimal reduction to the level of service at the intersections.2020/012020/02
Image
Construction
02091Flashing Yellow Left Turn Arrow RetrofitRetrofit and upgrade thirty-nine (39) Protected/Permissive signalized intersections with Flashing Yellow Left Turn Arrow displays to meet current standards.2020/012020/05
Image
Construction
02101Laguna Treatment Plant Digester Gas Conditioning ImprovementsDigester gas flows to the CHP facility have increased since the commissioning of the High Strength Waste facility. The increased gas flows have shown a need to improve/upgrade certain components of the Plant digester gas conditioning equipment. Design requirements as determined by engineering consultant will be required.2018/122019/11
Image
Construction
02105Laguna Treatment Plant Chillers and Climate Control Upgrades at Administration and Annex BuildingThree chillers, two boilers and associated control equipment have reached the end of their service life as identified in recently completed condition assessment report. One chiller is located inside the Annex Building and two chillers are located outside the rear of the Administration Building. The new chillers and boilers will have greatly increased operating efficiencies and the Programmable Logic Contoller upgrades will allow programming by in-house staff. The ability to troubleshoot and rectify control problems in-house will result in more timely climate control and reduced expenditures for outside contract assistance.2020/032020/08
Image
Proposed
02117S Fulton Trunk Sewer Repair - Fulton Rd at Santa Rosa CrkEliminate the constrictions in the existing sewer pipe across Santa Rosa Creek between manhole 12 and manhole 13. The existing 18-inch ACP sewer was installed in 1969 under the creek and west of the Fulton Road bridge. The 18-inch ACP sewer was lined with a 14-inch polyethylene (PE) liner in 1985. CCTV video indicates that the PE liner is deformed creating constrictions. Open-cut replacement with a new 8-inch diameter pipe was the method recommended by the consultants RMC/Woodward & Curran in their Technical Memorandum dated February 26, 2018. A cofferdam, fish relocation, and construction area creek flow bypass will likely be necessary.2022/042022/12
Image
Construction
02131Accessibility Alterations at Howarth ParkRemove, grade and construct concrete pathways at Howarth park for the purpose of compliance with accessibility standards. The proposed area of alteration includes: 1) Alterations to the loading area at the train station for an accessible train car. 2) The area around the Carousel. 3) An accessible route to the animal barn and pony rides. 4) A ramp system through the picnic area by the carousel.2019/112020/03
Image
Construction
02137Oakmont Dr. Sewer Main Upsizing Oakmont Creek to Greenfield CirReplace approximately 1188 feet of 6 inch asbestos cement sewer main with 10 inch PVC in Oakmont Drive (Oakmont Creek to Greenfield Circle) as this section is undersized and has resulted in two sanitary sewer overflows since 2009. Pedestrian ramps will be upgraded to current standards within the project limits.2019/092019/11
Image
Construction
02146City Hall Campus Sidewalk Reconstruction Phase 1The project will upgrade sidewalk, driveways and curb ramps at the following locations: 90 Santa Rosa Ave (west side only), 635 First Street (east side only), and Parking Garage 9 (D Street side only.)2020/032020/04
Image
Construction
02150Station 2 Emergency Generator Replacement and Station 3 Power Filter InstallationThis project will install a filter to eliminate harmonic feedback to insure proper operation of the emergency generator at the Station 3 pump station. Additionally, this project will replace the existing emergency generator at Station 2.2019/022019/11
Image
Proposed
02184Permanent Fire Station 5 RebuildClear debris and facilities damaged from the Tubbs fire and re-construct Fire Station 5.2021/072023/07
Image
Proposed
02188Parking Garage 12 Elevator ModernizationModernize both elevators in City Parking Garage 12 including replacing controllers, soft starters, signal fixtures, cab flooring, light fixtures and hydraulic assembly.2020/032020/06
Image
Construction
02193Laguna Treatment Plant Digester 1 ReroofThe roofing and insulation on the floating roofs (covers) on Digester Nos. 1 & 2 has reached the end of its service life. The roofing membrane will be replaced (excluding insulation) on Digester 1 this year and is intended to extend the life of the floating cover until a fixed cover can be installed in the future.2019/102019/11
Image
Construction
02198Bicycle and Pedestrian Gap Closures - Piner Rd and Dutton AveThe project has two locations. The first location will rehabilitate the outside lanes of pavement and provide bicycle lanes on Piner Road between Coffey Lane and Range Avenue. The second location will provide a sidewalk on the east side of Dutton Avenue just south of Jennings Avenue. Both locations will include upgrading the curb ramps to current standards.2019/122020/03
Image
Proposed
02201Skyfarm A and Hansford Lift Stations Reconstructions-Fire RelatedTwo lift stations were severely damage during the Tubbs Fire. One is located on SkyFarm Drive near Saint Andrews Drive and the other at the end of Hansford Court. They both must be reconstructed.2020/032021/05
Image
Construction
02204EGW Freeway WellThe purpose of this project is to implement the City's Groundwater Master Plan by utilizing a State grant and local matching funds to evaluate known and potential water quality risks in the vicinity of the Freeway Well and study the feasibility of groundwater cleanup, protection, and/or development (to replace Freeway Well in kind) to ensure adequate emergency water supply, particularly for the northeast area of Santa Rosa. This project will examine the area around the Freeway Well to more fully characterize the groundwater contamination problem, better understand the lithology and deep aquifer hydrology, and provide additional groundwater sampling and data analysis.2019/102019/12
Image
Proposed
02208Fire-Related Repairs of Utility StationsSeveral potable water stations, reservoirs and sewer lift stations sustained damage during the Tubbs Fire. This project will undertake rehabilitation efforts at the affected sites.2020/042021/04
Image
Construction
02223Installation of Public Restroom in Downtown AreaInstallation of The Portland Loo, a 24-hour prefabricated single-occupant public restroom. The restroom will be installed in front of City Hall Annex at 90 Santa Rosa Avenue. Installation includes utility connections, foundation for the restroom and accessibility.2020/012020/11
Image
Proposed
02227Fire Damage Storm Drain Repairs- CitywideThis project will repair fire damaged storm drain drop inlets at 18 locations.2020/092020/10
Image
Construction
02233Fire Damaged Street Lights Replacement In Coffey ParkThis project will replace 229 fire damaged street lights in the Coffey Park area.2020/022020/08
Image
Proposed
02245Asphalt Spot Repairs of Actual Burned AreasThis project will repair the burned asphalt concrete pavement in the Coffey Park and Fountaingrove areas.2020/062020/08
Image
Construction
02246Fire Damaged Street Lights Replacement In FountaingroveThis project will replace 40 fire damaged wood pole street lights in the Fountaingrove area.2020/022020/07
Image
Proposed
02247Cross Creek Vehicle Bridge Fence RepairThis project will replaced the fence above the culvert on Cross Creek Rd at Ribeli Creek on upstream side as the result from the fire damage.N/AN/A
Image
Proposed
02252Pavement Preventive Maintenance 2020This project will consist of performing preventive maintenance on City streets by contract. Work to be completed is crack sealing, asphalt dig outs, and pavement resurfacing.2020/042020/06
Image
Construction
02254Stony Point Rd Utility Box Adjustments and Sidewalk RepairsComplete sidewalk gap closures and utility box adjustments.N/AN/A
Image
Construction
02267Coffey Neighborhood ParkThis project removes wind and fire blown physical hazards from the Coffey Park turf areas, and reconstructs the park in accordance with the Coffey Park Master Plan.2019/112020/08
Image
Proposed
02269Santa Rosa Consolidation ProjectThis project will connect nine community water systems to City water. Doing so will provide upgraded fire protection capabilities in each of the communities. This project is Prop 84 funded.2021/092022/09
Image
Proposed
02271Delta Pond Slope ProtectionWave action from wind and storm events have caused significant erosion benches on the northerly slope of reclaimed water Delta pond. The project consists of rehabilitating approximately 5,200 linear feet of Delta Pond northerly embankment and installation of a coffer dam. Rehabilitation method consists of excavating and compacting approximately 2.5 ft. of the slope embankment and placing approximately 1 ft. of rock rip rap over geotextile to protect the embankment from wave erosion and vegetation.2020/082023/12
Image
Proposed
02287Fire-Damaged Tree Removal- Parks, Open Space, ROWThis project will remove fire damaged trees from City Parks and other City owned parcels.2020/062020/07
Image
Proposed
02318Annual Slurry Seal 2020This project will apply slurry seal to various (primarily residential) City streets. Streets are slurried by applying a thin, quarter-inch roadway coating of liquid asphalt and sand. Slurry seal restores the pavement's ability to prevent water intrusion, corrects minor cracking and improves skid resistance. Priorities are established by the Pavement Management System.2020/072020/08

Santa Rosa City Hall - 100 Santa Rosa Avenue - Santa Rosa, CA 95404