Capital Improvement Projects List - All

Image NOTE: The list of public facilities improvement projects shown below contains projects that have completed the necessary budgetary and environmental approval process, as well as those proposed for construction. Appearance of a project on this list does not constitute final approval of any project. Each project is subject to environmental and engineering review to be conducted in accordance with the applicable requirements of the California Environmental Quality Act (CEQA), and City Code provisions.

To find out about a few Recreation & Parks projects not listed here, visit www.srcity.org/parks.

Click a Project ID in the table below to see the project web-page report.

Down arrow imageClick a column header to turn on sorting. Year/Month.
StatusProjIDTitleDescriptionEst StartEst End
Image
Proposed
00080Emergency Groundwater Supply DevelopmentThis is a multi-year project to locate and construct multiple groundwater wells to provide a backup water supply in the event of a natural disaster or other event that disrupts the City's water supply from the Sonoma County Water Agency.2014/012029/01
Image
Proposed
00158North Trunk Sewer Replacement - Mendocino Ave to Terra Linda DrThis project will address the existing lack of accessibility to the North Trunk Sewer main for routine maintenance and subject to risks associated with traversing adjacent and/or under an existing watercourse. The project will relocate the existing 1,650 ft. of 12 inch to 15 inch vitrified clay pipe (VCP) sewer main located adjacent to Paulin Creek.2018/032019/06
Image
Proposed
00284Laguna Treatment Plant Ultraviolet Disinfection ReplacementDue to recent regulatory changes, the existing UV system needs augmentation in order to meet capacity requirements during peak wet weather flows. The purpose of the Request for Proposal (RFP) is to accept qualifications and proposals from interested parties seeking to furnish all components required to provide a complete operable Low Pressure, High Output Ultraviolet Disinfection Equipment Systems for the City of Santa Rosa's (CITY) Laguna Treatment Plant. This RFP will provide the means to select a System, establish and hold pricing through a Memorandum of Understanding for the selected System that will allow CITY to brand name specify the System in a construction contract CITY will award in 2018.2018/042019/09
Image
Proposed
00544Santa Rosa Regional Water Reuse Plant Flood ProtectionThis project will install flood protection facilities for the Santa Rosa Regional Water Reuse Plant (WRP) (formerly known as the Laguna Treatment Plant), the Geysers and Reclamation Pump Stations, and Biosolids facility. The flood protection may include walls and berms as recommended in the "Flood Protection at the Laguna Treatment Plant Feasibility Study" that was completed in July, 2016.2019/092020/11
Image
Construction
00568Seismic Upgrades and Improvements Phase 4 - R3, R7 & R12B And Various Other Site Improvements - S1, S2, R6 & R12AThis project involves seismic retrofits and structural improvement upgrades to water reservoirs (R3, R7, R12B) to meet current seismic safety codes and requirements. In addition, site improvements addressing site security at R12A and minor drainage and accessibility concerns are proposed at each site, as well as coating improvements to the roof of water reservoir R6.2017/082018/03
Image
Proposed
00661Pacific Ave Reconstruction - Humboldt St to Montecito AvePacific Avenue will be reconstructed between Humboldt Street and Montecito Avenue. Curb ramps will be reconstructed at all intersections to meet current state and federal accessibility standards. The project will also include replacement of a short section of sewer main as well as water services.2019/062019/10
Image
Construction
00685Garage 9 - Hazardous Materials (investigation)This project is a Regional Water Quality Control Board mandated soil and groundwater study and remediation of petroleum contamination under the multi story parking garage.2019/062019/10
Image
Construction
00702Courthouse Square ReunificationThe Courthouse Square project will reunify the existing areas at Courthouse Square that are currently bisected by Mendocino Avenue. Side streets with diagonal parking will be constructed on the east and west sides of the square. The reunited Courthouse Square will be a central gathering place where residents and visitors can enjoy a wide variety of community events such as farmers' markets, concerts and outdoor area exhibits.2016/052017/04
Image
Proposed
00720Hearn Ave at Highway 101 - Phase 3 Rebuild InterchangeThe existing Hearn Avenue interchange at Highway 101 will be rebuilt to ease traffic congestion and improve clearance over the highway. Improvements to the overpass and approaches will include widening to four vehicle lanes, with bike lanes and sidewalk on both sides.2016/052017/04
Image
Construction
00727Stony Point Road Widening and Reconstruction Phase 2 - Sebastopol Road to Hearn AveThe purpose of this project will be to ease traffic congestion by widening Stony Point Road to four lanes from Hearn Avenue to Sebastopol Road. The addition of travel and turn lanes, new sidewalks, bicycle lanes, and updated traffic signal upgrades will increase road safety along this vital north-south corridor. The project also includes the installation of new water main and water services, sewer main stubs to currently undeveloped parcels and storm drains.2015/082017/12
Image
Proposed
00769Highway 101 Bike/Pedestrian OvercrossingA pedestrian and bicycle bridge crossing over U.S. 101 will connect the northern half of the City Rosa to residential, commercial, and academic institutions while providing safe and unimpeded bicycle access from high vehicular volumes at the U.S. 101 interchanges.2015/082017/12
Image
Construction
01137Bridge Repair - Deck TreatmentProject provides preventive maintenance for concrete bridge decks ensuring long-term durability and prevention of deterioration due to rebar corrosion for six bridges.2017/072017/09
Image
Proposed
01178Fulton Rd from Guerneville Rd to Piner Rd - Widen to Four LanesThe purpose of this project is to ease future traffic congestion. Fulton Road will be reconstructed and widened to 4 lanes with bike lanes and sidewalks between Guerneville Road and Piner Road. The project includes a median island and storm drain improvements.2017/072017/09
Image
Proposed
01459Mohawk Lift Station and Forcemain Realignment - Phase IIThis project replaces aged sewer mains and antiquated water mains in Yuma St between Seneca Ln and Sioux St, in all of Sioux St, and in Mohawk St between Cherokee Ave and Comanche St. This project will remove approximately 70 homes from the Mohawk Lift station sewer shed. All streets will be reconstructed. In addition, the Mohawk Lift station will be upgraded to replace the deteriorated wet well and to install newer more efficient pumps.2017/102017/12
Image
Proposed
01549Inspection of Bridge Assets: Structural CrossingsContinuous maintenance work and assessments on various pedestrian bridges and culverts throughout the City.2017/102017/12
Image
Proposed
01568Augustan, El Camino and Grosse Sewer and Water ReplacementThis project is part of the replacement of the Grace neighborhood water and sewer mains. This project will replace aged sewer and water mains in Augustan Avenue, El Camino Way from Grosse Avenue to Augustan Avenue, and in Grosse Avenue from El Camino Way to Dowling Court. This project will abandon an inaccessible backyard easement and re-plumb the tributary lots to the public sewer in the street. Ten dpdestrian ramps will be replaced. All streets will be reconstructed.2018/082019/08
Image
Construction
01570Spring Lake Lift Station ImprovementsA geotechnical investigation has provided a design scope to repair ground settlement at the Spring Lake Lift Station. This project will remove several feet of soil and replace it with a suitable compacted granular fill. Upgrades to the lift station will include new controls, backup generator, lighting, fencing, and a new concrete pad for the station with asphalt concrete pavement on the remainder of the site. 2017/072018/01
Image
Construction
01627Downtown Santa Rosa StreetscapeThis project has two locations, one is on 3rd St between Morgan and B St, involving pedestrian improvements including lighting, street trees, bike lanes and delineation to channelize pedestrians to the north side of 3rd St at Morgan St and at B St. The second location is at Santa Rosa Avenue and Mill Street where a new traffic signal will be installed along with pedestrian ramps, and storm drain improvements.2017/072018/01
Image
Proposed
01675Montgomery Dr Water Replacement - Mission Blvd to Jackson DrThis project will replace a parallel 4" steel water (1947) main and a 6" ACP water main (1969) with a single 8" water main from Montgomery Drive and from Mission Boulevard to Jackson Drive. The 4" steel main is of primary concern and a new single main will reduce maintenance costs.2017/102017/11
Image
Proposed
01801R7 Road Access Stabilization RepairsThe purpose of this project is to provide soil and slope stability improvements along the access road to water storage tank R7 and provide drainage improvements from the tank site to St. Francis Road.2018/032019/01
Image
Proposed
01805Oakmont Treatment Plant Sewer Trunk RelocationThis project will install a new sewer trunk line in order to by-pass the Oakmont Treatment Plant. The existing plant by-pass line has several elevation changes and causes solids to build-up, reducing flow, requiring local operation crews to conduct routine cleaning and flushing of the sewer trunk. A new bypass trunk line would greatly reduce maintenance costs and the possibility of sanitary sewer overflows.2018/062018/10
Image
Proposed
01817Fulton Rd Sidewalk Improvements - College Ave to Santa Rosa Creek TrailThis project will provide sidewalk along the west side of Fulton Road from College Avenue to the existing driveway for the Santa Rosa Creek Trail.2017/102017/11
Image
Construction
01839Farmers Ln Well Facility RehabilitationThe Farmers Lane Wells and Treatment Plant needs rehabilitation to restore the wells production capacity. This project focuses on the needed rehabilitation for the well facilities with a separate project to focus on the treatment plant rehabilitation in FY 18/19. The work to be completed for rehabilitating the wells includes replacing the existing pumps with a submersible pump at W4-1 and a vertical in-line pump at W4-2; installing new electrical service; and replacing/expanding the buildings to house the new electrical components on-site.2017/102018/05
Image
Proposed
01869Crosswalk Enhancements Throughout Santa RosaThe purpose of this project is to enhance pedestrian crossings and bring additional awareness to drivers of potential pedestrian use.2017/092017/12
Image
Construction
01870Santa Rosa Cmplt Sts Road Diet on Transit CorridorThis project will repave W. Third Street from 1,100 feet west of Dutton Avenue to Roberts Avenue and Mendocino Avenue from Steele Lane to Administration Drive. Curb ramps will be constructed to meet current standards in both locations. W. Third Street will be restriped to include a single travel lane in each direction, a two-way center turn lane, Class-2 bicycle lanes and street parking.2017/082017/11
Image
Construction
01896W 6th St at Madison St Sewer and Water ImprovementsThis project replaces aged sewer and water mains and will reduce system maintenance costs. All mains and laterals will be replaced and the pavement area will be reconstructed.2017/102017/11
Image
Proposed
01897W. College Ave from Marlow Rd to Kowell St - Pedestrian PathThis project will build pedestrian paths or sidewalks between Marlow Rd and Kowell St along W. College Ave to close the pedestrian gaps along that segment of roadway.2020/062020/08
Image
Proposed
01899Guerneville Rd Pedestrian PathThis project will build pedestrian paths or sidewalks to close existing sidewalk gaps on Guerneville Road between Marlow Road and Ridley Avenue.2018/042018/05
Image
Proposed
01903Los Alamos Trunk Replacement: Streamside Dr to Elaine DrThis project includes providing the preliminary design and supporting studies for replacement of the existing Los Alamos sewer trunk from Streamside Drive to Melita Drive (approximately 16,000 linear feet (LF)). Construction documents will be prepared for the downstream segment (approximately 5,500 LF) from Streamside Drive to Elaine Drive. The trunk, installed in the 1950's is undersized and is in poor condition. This project will provide more capacity to help prevent overflows, increase reliability, and reduce maintenance. In addition, it will be re-aligned out of yards and further away from the creek where practical. Relocation of the water main may be necessary in certain locations to create adequate separation from proposed sewer line.2018/092020/02
Image
Proposed
01904Los Alamos Trunk Replacement: Elaine Dr to Melita Rd at Santa Rosa CreekThe purpose of this project is to replace an outdated and undersized section of the Los Alamos Sewer Trunk, which runs north of and parallel to Santa Rosa Creek from Elaine Drive to Melita Road. This project will provide trunk capacity, increase reliability and reduce maintenance. Relocation of the water main to create adequate separation from proposed sewer line is anticipated.2022/042024/04
Image
Proposed
01909Slope Protection on Northerly Slopes of Ponds C, D, and DeltaThe northerly slopes of Delta Pond, and Ponds C and D, need protection from further erosion created by wave action from storm events. Evaluation of placing rock slope protection in a band above and below the ponds operating surfaces, rather than from the toe of the pond, will be investigated and considered to reduce project costs.2018/062020/11
Image
Proposed
01924Lower Colgan Creek Restoration - Phase 2This restoration project will restore 2,170 lineal feet of straightened and denuded channel into a natural creek while still providing flood protection. This project is the second phase of a three phase project. The new alignment will allow the creek channel to have greater water retention during high flows. There will be in-stream structures and pools installed to enhance aquatic life such as boulders, boulder weirs, and over 1,000 native trees, shrubs and grasses. Project limits are from Victoria Drive downstream to Boron Avenue.2018/062020/11
Image
Construction
01931City Hall Plaza Demonstration Garden and LID RetrofitThe City of Santa Rosa has received a State Water Resources Control Board Stormwater Grant. The project will convert two of the large lawn areas at City Hall to a low water use demonstration garden and retrofit the main parking lot to capture and treat stormwater runoff. Additionally, this project will include a rainwater harvesting demonstration feature, a public gathering area for educational classes, signage and kiosks throughout the campus, as well as a web-based educational interface.2016/082017/03
Image
Proposed
01943Vallejo Street Trunk Sewer Junction Structure ModificationsThe sewer junction structure for the Crosstown and Bennett Valley Trunks has only one access point for maintenance at the incoming line on the Crosstown Trunk but not on the incoming Bennett Valley Trunk nor on the outgoing combined flow trunk. The additional two access points in the junction structure will greatly improve visual inspections and facilitate cleaning and maintenance for the entire junction structure and connecting trunk mains.2017/102018/08
Image
Construction
01944Sewer Main Lining, Manhole and Lateral Rehab At Various Locations 2016This project will focus on the rehabilitation and/or improvement of sewer mains at various locations in the city. The project will rehabilitate approximately 5,685 feet of pipeline by cured-in-place pipe (CIPP) lining inserted into the existing sewer main pipe at 11 locations throughout the city; 41 manholes are to be rehabilitated and/or improved that are either connected to the pipelines to be CIPP lined or at locations selected by the City; and 6 sewer laterals are to be rehabilitated at three of the project locations.2017/072017/11
Image
Construction
01952Geysers Pipeline Stabilization - Eastside RoadThis project will address a 150' section of the Geysers pipeline alignment along Eastside Road.2017/072017/08
Image
Construction
01964SMART Bus Turnout - Guerneville RoadThis project will construct a bus turnout on Guerneville between the SMART rail and Herbert Lane. This is to be constructed prior to the implementation of rail passenger service and will accommodate the potential for up to 2 buses to stage in the turnout. The project will consist of an approximately 150 foot long turnout, the reconstruction of curb, gutter, and sidewalk, the relocation of a streetlight, power pole, tree removal and the installation of bus shelters. The bike lane will remain in its current alignment. Right of way has been acquired for this project.2017/072017/08
Image
Proposed
01965Emergency Well Pump Station- A Place to PlayThe purpose of this project is to convert the existing test well to an Emergency Groundwater Well, along with design and construction of a well pump station and apurtenences associated with the Emergency Groundwater Well at A Place to Play Park.This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water's Groundwater website located at: http://ci.santa-rosa.ca.us/857/Groundwater2017/122018/07
Image
Proposed
01999Cobblestone Dr Zone R2-R4 Water Main ConnectionSeveral fire hydrants serving approximately 32 homes at the north end of Cobblestone Dr have sub-optimal fire flow ranging from approximately 752 gpm at 20 psi to 1329 gpm at 20 psi. A new 8" pipeline is proposed to connect the existing pipeline in Tillmont Way (or less likely, Kelsey Knolls) (located in the City's Pressure Zone R2) to the existing 6-inch diameter pipeline located in Cobblestone Drive (located in Pressure Zone R4). A new pressure regulator with 1 1/2" bleed (to keep water circulating) is required to maintain the pressure zone break between R2 and R4.2019/082019/11
Image
Proposed
02004Alvarado Ave and Vallejo St Water and Sewer ImprovementsUpsize water mains on Vallejo St and Mount Olive Dr to meet fire flow requirements as identified in the 2014 Water Master Plan.2018/032018/08
Image
Construction
02007Underground Tank Remediation 650 4th StreetTo investigate what is suspected to be an old, unpermitted heating oil tank under the sidewalk in front of 650 4th Street. If it is a tank, then it will be abandoned under Fire Department oversight.2016/082017/09
Image
Construction
02012Alpha Farm Biosolids Storage Facility Fire Sprinkler System Freeze ProtectionThis project will retrofit the wet fire suppression system with a freeze protection system at the Alpha Barn Alpha Farm Biosolids Storage Facility. This improvement will prevent water damage which could be caused by pipes bursting during the below freezing winter temperatures.2017/102018/02
Image
Proposed
02015Seal Coat Water and Sewer Stations, Fire Training Center, and Parking Lots 13,14 & DepotIn an effort to preserve paved areas around City of Santa Rosa infrastructure, the City plans to slurry seal paved areas around several water reservoir and sewer and water pump station locations as well as the Santa Rosa Fire Department's fire training center. Slurry seal is a thin coat (T=0.25") of asphaltic emulsion and fine aggregate that covers exposed aggregate, seals cracks, prevents moisture intrusion and increases skid resistance. Please click the link below titled "Seal Coat Water and Sewer Stations, Fire Training Center, and Parking Lots 13, 14 & Depot Addresses" for name and address of each project site.2017/102017/10
Image
Construction
02064Laguna Treatment Plant - Primary Treatment Structure Upgrade - Phase 1This project will involve removing a portion of the above-ground (floor level) cast-in-place superstructure above the Secondary Sedimentation Basins of the Primary treatment building. A previously performed condition assessment, specific to the Subregional Plant facilities, determined a critical need to improve this building and meet current seismic safety codes and requirements to prevent major injury, loss of life and/or disruption in plant processes.2016/082017/09
Image
Proposed
02067Corporation Yard SecurityThis project includes the installation of key card access at several points of entry, upgrading surveillance cameras, and replacing the main entry gates at the City's Municipal Corporation Yard.2017/062017/12
Image
Proposed
020702018 Streets InitiativeThe project will provide pavement maintenance using various treatments to prolong the life of City streets. Pavement preservation maximizes limited resources by avoiding the necessity for costlier repairs. The City made a commitment to our streets with a $3 million general fund investment in the Neighborhood Streets Initiative in the 2016-17 CIP budget. This project continues that commitment with a smaller ongoing amount of general fund investment in the City's streets. This investment will demonstrate leadership in pavement maintenance to the City's peers at SCTA and MTC. It will also ensure that the City meets the annual Measure M Maintenance of Effort requirement, allowing the City to continue receiving over $1M per year of Measure M funds for pavement maintenance.2017/062017/12
Image
Proposed
02076Range Ave Sewer Main Replacement north of Russell AveInstall 339 feet of 8" PVC in Range Ave to replace aged, deteriorated and root infested vitrified clay pipe.2017/062017/12
Image
Construction
02079Farmers Lane Well Facility Pump Replacement ProjectIn order to meet the proposed construction schedule for the Farmers Lane Well Rehabilitation Project, the well pumps will need to be pre-purchased due to the long lead time. A submersible pump is planned to be installed in W4-1 with a nominal pumping capacity of about 840 gpm. A vertical turbine pump is planned to be installed in W4-2 with a nominal capacity of about 1,660 gpm, providing a total capacity of 2,500 gpm.2017/102018/05
Image
Construction
02081Post Ct and Simpson Pl Sewer ReplacementsPost Ct Sewer Replacement: Post court involves replacement of 130 feet in Fernglen (PTP) and approximately 150 feet of sewer main in Post court along with 6 sewer laterals to be replaced. Post Court will be reconstructed, 8" sewer main to be installed. Simpson Place Sewer Main Replacement Replace approximately 310 feet of sewer main. This project is located in the Lincoln Manor section of Simpson Pl. The purpose of this project is to eliminate dips and deteriorated invert in existing AC pipe.2017/102017/11
Image
Construction
02082Accessibility Alterations at Skyhawk ParkThis project requires removal and reconstruction of approximately 740 lineal feet of existing concrete pathways adjacent to Mountain Hawk Drive; and approximately 400 lineal feet of existing asphalt pathways near the soccer field for the purpose of compliance with the Americans with Disabilities Act. The pathways will be reconstructed within the same footprint as the existing pathways using concrete construction, except for a 25 lineal foot pathway addition to provide disability access to the existing north soccer field. Minor grading is expected at the pathways near the soccer field to correct slope. Grading work will require the removal of two trees growing adjacent to the pathway.2017/032017/07
Image
Proposed
02083Emergency Groundwater Wells at Oakmont Treatment Plant and Speers RdThis project is intended to provide the City of Santa Rosa with two investigative boreholes, on two different parcels in Northeast Santa Rosa, to evaluate the viability of installing emergency wells or monitoring wells. This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water's Groundwater website located at: http://ci.santa-rosa.ca.us/857/Groundwater2018/042018/08
Image
Construction
02086Neighborhood Streets Initiative and Roseland Street OverlayThis project will rehabilitate approximately 2.35 miles of selected city streets. Proposed improvements vary between roadway reconstruction and asphalt concrete overlay. Curb ramps within the project limits will be upgraded to the current ADA standards, a total of 73 ramps. All existing striping will be reinstalled once the streets are resurfaced.2018/042018/08
Image
Proposed
02117Fulton Trunk Lining - Fulton Rd at Santa Rosa CrkRepair failed liner in 18" Trunk under Santa Rosa Creek. Potential solutions being studied include cutting out old liner and installing a new one, slip-lining the existing liner with a smaller diameter pipe, installing a pump station and abandoning the trunk crossing, etc.2019/102020/09
Image
Proposed
02122Pavement Preventive Maintenance 2017This project will consist of performing preventive maintenance on City streets by contract. Work to be completed is crack sealing, asphalt dig outs, and pavement resurfacing.2017/092017/11
Image
Construction
02144Water Main Lowering- Rose AvenueWater main lowering on Rose Avenue to facilitate the roadway reconstruction portion of the Stony Point Road Widening and Reconstruction Phase 2 Sebastopol Road to Hearn Ave project (PID 727).2017/082017/09

Santa Rosa City Hall - 100 Santa Rosa Avenue - Santa Rosa, CA 95404